|
Time hour/min |
| |
|
|
| |
|
. | ||
|
1:25 |
Remove ALESP from LM |
Remove RTG fuel from LM |
|
1:40 |
Drive LRV to ALSEP site |
Carry ALSEP to its site |
|
1:50 |
Connect RTG to central station |
HFE drill 1 hole |
|
2:00 |
Deploy LSM |
HFE emplace and connect probe 1 |
|
2:20 |
Install central station |
HFE emplace and connect probe 1 |
|
2:30 |
Install central station |
HFE set up equipment drill 2 hole |
|
2:40 |
Install central station |
HFE emplace and connect probe 2 |
|
2:50 |
ASK implant geophones |
ASK implant geophones |
|
3:00 |
ASK thumper |
ALSEP photos |
|
3:10 |
ASK thumper |
ALSEP photos |
|
3:20 |
ASK thumper |
ALSEP photos |
|
3:30 |
ASK thumper |
ALSEP photos |
|
3:40 |
ASK set up mortar |
Deep core drilling |
|
3:50 |
Core recovery |
Drilling. Core recovery |
|
4:00 |
Core recovery |
Core recovery |