|
|
|
Saturn Illustrated Chronology - Part 6
January 1965 through December 1965
|
1965
January
Two Saturn IB test stages arrived at MSFC on January 4, 1965;
the S-IB dynamic/facilities checkout stage, S-IB-D/F, from Chrysler Corporation's
Space Division at Michoud and the S-IVB dynamic stage, S-IVB-D, from Douglas. |
|
218 |
218. Saturn stages in route
to MSFC by barge
219. Pegasus with wings
fully extended |
On January 7, ME Lab began structural fabrication of
S-IU-200S/500S.
On January 13 technicians at KSC attached Pegasus A, encased
in its Apollo service module shroud and adapter, to the S-IV-9 stage in
preparation for scheduled launch. The following day at Launch Complex 37B
technicians mated the Apollo BP-16 command module to the Apollo Saturn
(AS-9) vehicle.207
207. NASA, MSFC, The Meteoroid Satellite Project Pegasus
First Summary Report, NASA TN D-3505, Nov. 1966, pp. 4-6.
|
219 |
At Douglas Aircraft Company's Sacramento
Test Center on January 21 there was a successful full-duration static firing
for 480 seconds of the Saturn I S-IV-10 stage. On this same date the S-IB
stage contractor, Chrysler, began clustering propellant tanks for the S-IB-3
at the Michoud Facility and, at MSFC, ME technicians completed assembly
of the S-IU-10 and structural fabrication of S-IU-200D/500D and began component
assembly on the latter.208
208. MSFC, Michoud Assembly Facility Historical Report,
January 1, 1965-June 30, 1965, pp. 7 and 23. Hereafter cited as MSFC,
MAF Hist. Report, Jan. 1-June 30, 1965.
|
220
220. Assembly of S-IU-200D/500D
for the Saturn IB and Saturn V |
MSFC completed negotiations with Douglas
on January 28 for the remaining eight S-IVB/IB stages and a set of ground
support eequipment. Another Saturn IB milestone on this date occurred when
KSC awarded R. E. Clarson, Inc., a $2,179,000 contract for Phase II modification
of the Launch Complex 34 service structure to support Saturn IB launches.209
209. KSC, Technical Progress Report, First Quarter
CY 1965, pp. 9-13.
Workmen at Seal Beach, California, on January 31 completed
assembly of the S-II-S stage five days ahead of schedule.
February
MSFC on February 1 completed component assembly of the instrument
unit, S-IU-200D/500D, for the Saturn IB and Saturn V dynamic test. NASA
began February of 1965 with several Saturn milestones. On February 19 the
space agency amended Chrysler's S-I/S-IB contract (NAS8-4016) to include
prelaunch checkout support, an amendment that added about $34,642,878 to
the contract cost.210 Also in the Saturn program, effective
this date, MSFC announced the following major revisions in the S-II stage
program: cancellation of the dynamic test stage, S-II-D; substitution of
the structural test stage, S-II-S, as a dynamic stage; transfer of the
all-systems test stage, S-II-T, from Santa Susana to Mississippi Test Operations;
assignment of the facilities checkout stage, S-II-F, directly to KSC; and
scheduling of an end to the electro-mechanical mockup test program.211
210. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
pp. 10-14.
211. U.S. Congress, House Subcommittee on Manned Space
Flight of the Comm. on Science and Astronautics, Hearing on H. R. 12718
(Superceded by H. R. 14324) No. 4-Part 2, 89th Cong., 2nd Sess., Washington,
GPO, Feb. 18, 24; Mar. 1, 2, 3, and 31, 1966.
On February 2 Chrysler at Michoud completed pre-static checkout
of the first S-IB stage, S-IB-1, and began preparations for shipping it
to MSFC for static tests.212 Across the country in the Saturn
V program North American Aviation's S&ID began transfer of the S-II-S
stage from the vertical assembly building at Seal Beach to the structural
test tower, a task completed on February 3.213 On this same
date ME technicians prepared the S-IU-8 for shipment to KSC.
212. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
p. 6.
213. NAA S&ID, Saturn S-II Stage MPR, Feb. 1965,
p. 39.
Workmen at Seal Beach completed on February 5 the S-II-S
stage, first ground test stage in the Saturn S-II stage program.
The Mobile District, U.S. Army Corps of Engineers, awarded
a $4.3 million contract February 8 covering construction of the S-II stage
Service and Vertical Checkout Building and the Cryogenic Barge Service
Building at Mississippi Test Operations.214 On this same date
S-IU-200F/500F component assembly began at MSFC. Also technicians completed
structural fabrication of S-IU-200S/500S.
214. MSFC, Mississippi Test Facility Historical Report,
January-December 1965, pp. 1 and 9-13.
|
|
221 |
221. Cryogenic dock at
MTO after completion |
Douglas completed final assembly of the S-IVB facilities
checkout stage, S-IVB-500F, on February 12 and turned the stage over to
NASA at Seal Beach. Workmen then loaded it aboard the NASA barge Orion
for transportation to SACTO.215 At KSC technicians completed
the countdown demonstration test for SA-9.
215. DAC, Saturn S-IVB Monthly TPR, Feb. 1966,
p. 2.
With launch only two days off, MSFC and Fairchild Hiller
Corporation technicians at KSC modified Pegasus A on February 14 so that
one frame or logic group of the wing panels could serve as a detector for
radiation-induced meteoroids.216
216. NASA MSFC, The Meteoroid Satellite Project Pegasus
First Summary Report, NASA TN D-3505, Nov. 1966, pp. 42-60.
|
|
222 |
222. Meteoroid measurement
capsule |
On February 16 NASA launched from KSC the Saturn I SA-9
vehicle. It performed excellently during the flight and placed the Apollo
boilerplate spacecraft, BP-16, and the first Pegasus satellite into separate
orbits. The Pegasus A satellite deployed its "wings" to a span of 96 feet
and exposed 2,300 square feet of instrumented surface to gather meteoroid
data, sort the information, and transmit it to earth receiving stations.
NASA launched SA-9 instead of SA-8 on this date because SA-9's S-I stage,
built in-house, had progressed through manufacture and testing more rapidly
than had S-I-8.217
217. F. A. Speer, Chairman, Flight Evaluation Working
Group, MSFC, to Dr. G. E. Mueller, Assoc. Adm., NASA, et al, teletype,
subj: "SA-9 Flight Results," Feb. 19, 1965; Speer to Mueller, subj: "SA-9
Flight Results," Feb. 26, 1965.
The S-IVB-500F arrived at SACTO February 17 and installation
began in Beta III test stand. On February 19 MSFC ME Lab began structural
fabrication of S-IU-500FS.
Douglas shipped S-IV-8 to KSC from SACTO on February 23.218
Also on this date Douglas personnel completed post-static checkout and
repair of the S-IV-10 stage and removed the stage from test stand Beta
II at SACTO. The following day Douglas initiated pre-static checkout of
the first flight S-IVB stage, S-IVB-201, at the Space Systems Center at
Huntington Beach.219
218. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
pp. 5 and 23.
219. MSFC Saturn I/IB Prog. Off., Saturn I/IB Prog.
Report, Oct. 1, 1964-Mar. 31, 1965, pp. 5 and 23.
|
223
223. SA-9 launch at Kennedy
Space Center |
On February 28 the first industry-produced
Saturn I first stage, S-I-8, arrived at KSC from Michoud.220
220. MSFC Saturn I/IB Prog. Off., Saturn I/IB Prog.
Report, Oct. 1, 1964-Mar. 31, 1965, p. 11.
During February fabrication of major structural subassemblies
for S-II-1 had begun at Seal Beach. Also during February NASA modified
the H-1 engine research and development contract to include uprating the
H-1 from 188,000 pounds thrust (188K) to 200K for Saturn IB application.
NASA approved modifications to the Rocketdyne H-1 engine production contract
converting it from cost-plus-fixed-fee (CPFF) to cost-plus-incentive-fee
(CPIF).221
221. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
pp. 5 and 23.
|
224
224. S-II-1 thrust structure
fabrication at Tulsa
225. S-IC-T en route from
ME lab to test stand |
March
On March 1, 1965, workmen ahead of schedule moved the S-IC-T
out of MSFC's ME Lab and on to the static test stand where they erected
it in the stand. The following day MSFC shipped the instrument unit for
SA-8 (S-IU-8) to KSC while technicians erected the S-I-8 stage on Launch
Complex 37B at the Cape.
The S-IB-1 stage left Michoud aboard the barge Palaemon
for MSFC on March 6. Eight days later the stage arrived at MSFC. Meanwhile,
on March 10, ME Lab technicians completed component assembly and structural
modification of S-IU-200S/500S.
On March 15 Chrysler technicians placed the S-IB-1 into
a static test stand at the MSFC complex in Huntsville, and began readying
the stage for static firing.222 This same date the S-IU-200S/500S
arrived at MSFC's structural test facility.
222. MSFC Press Release No. 65-43, Feb. 16, 1965.
KSC technicians at Launch Complex 37B on March 17 erected
the S-IV-8 stage and the S-IU-8 atop the S-I-8 stage and began a series
of systems tests including radio frequency checks, tanking procedures,
and simulated flights.223
223. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
p. 6.
Technicians at Michoud on March 24 installed the S-IC-D thrust
structure in the Vertical Assembly Building. |
225
226
226. Erection of S-IC-T in
test stand at MSFC
227. Saturn IB booster being
moved into static test stand |
| On March 26 NASA and Boeing signed a supplemental
agreement incorporating a new Saturn V delivery schedule called Plan VIII.
At MSFC, on March 29, S-IU-500V structural fabrication
began. The following day S-IU-500FS component assembly began. NASA on March
31 approved award of the Saturn IB/V instrument unit contract to IBM. This
contract (NAS8-1400) was the first major incentive contract to be negotiated
in the Saturn IB program.224
224. MSFC, MAF Hist. Report, Jan. 1-June 30, 1965,
pp. 5 and 23.
In March NASA delineated specific management roles for the
Saturn IB/Centaur System to MSFC and Lewis Research Center. MSFC received
project management for the Saturn IB/Centaur System and Lewis management
of the Centaur System. |
227 |
|
|
|
| SATURN
IB/CENTAUR |
229 |
THIRD
STAGE
CENTAUR CHARACTERISTICS |
| Prime
Contractor |
General
Dynamics
|
| Thrust |
30,000
LBS
|
| Weight |
3,600
LBS (Dry)
|
| Engines |
RL-10-A-3
(Two)
|
| Propellants |
LOX
& LH2
|
| PAYLOAD
CAPABILITIES |
| Lunar
Trajectory |
1?,000
LBS
|
Planetary
(Mars &
Venus) |
?,?00
LBS
|
|
228
228. Positioning S-IV on S-I at KSC
229. Saturn IB/Centaur configuration |
April
In the Saturn IB program on April 1 the S-IB-1 performed
successfully in its first static firing, with engine cutoff initiated by
the control operator after 35 seconds. Also on April 1 in the IB program
NASA authorized Rocketdyne to increase the 200K H-1 engine to 205K to support
Saturn IB application to even larger missions.225
225. IBM Space Systems Center, Saturn IU Program Plan,
Apr. 5, 1966, pp. 1.1-1.2.
|
|
230 |
230. Static firing of S-IB-1
at MSFC |
On April 7 Major General Samuel C. Phillips, Director,
Apollo Program, NASA, forwarded to MSFC an amendment to the FY 65 Research
and Development Appropriations. This authorized transfer of $5 million
to the Saturn IB Program for Saturn IB/Centaur design effort.226
226. MSFC Industrial Operations, Engine Program Office,
QPR, F-1, H-1, J-2, and RL10 Engines, January, February, and March,
1965, Mar. 15, 1965, pp. 15-16.
The first single-engine S-IC-T firing occurred at MSFC on
April 9.
Apollo spacecraft BP-26 arrived at KSC on April 10 and
entered receiving inspection. Also on this date MSFC successfully test
fired a single F-1 engine on the stage for 16.73 seconds. Three days later
Chrysler test personnel successfully static fired the S-IB-1 stage the
second time at MSFC; the test lasted 142 seconds. The next day, April 16,
Marshall personnel successfully test fired all five of the S-IC-T stage's
F-1 engines. This first S-IC-T five-engine test occurred two months ahead
of schedule and lasted 6.5 seconds.227
227. Maj. Gen. Samuel C. Phillips, Dir., Apollo Program
Off., NASA, to MSFC, Attn. Stan Reinartz, Saturn IB/Centaur Program Mgr.,
teletype, Apr. 7, 1965.
|
|
231 |
231. Static test of all
five
engines of Saturn V booster
(S-IC stage) |
On April 20 workmen loaded the S-IB-1 stage aboard the
Palaemon for its return trip to Michoud to undergo post-static checkout
and modification.228
228. MSFC Test Lab., Hist. Report, Jan.-Dec. 1965,
pp. 7-8.
Pegasus B, second of the micrometeoroid detection satellites,
arrived at KSC on April 21 to be readied for launch. |
|
232 |
232. Deployment sequence
of the Pegasus |
MSFC on April 22 began negotiating with Chrysler for
an equitable adjustment to contract NAS8-4016. This resulted from NASA
program redirection and termination of six S-I stages. Negotiations would
continue throughout 1965.
On April 24 the S-IB-1 arrived at Michoud from MSFC where
it had undergone static tests. On this same date, at Santa Susana, S&ID
conducted the first five-engine ignition test of the S-II battleship.229
229. MSFC Test Lab., Hist. Report, Jan.-Dec. 1965,
p. 1; Systems Static Test Branch, CCSD, Saturn S-IB Stage Final Static
Test Report, S-IB-1, June 4, 1965, pp. 1-2.
MSFC on April 29 completed assembly of the S-IU-200F/500F.
The S-IVB contractor loaded the first flight S-IVB stage
aboard the NASA barge Orion on April 30 for shipment to SACTO. Also
on April 30, during the final test of S-II-S at Seal Beach a failure occurred
that seriously damaged the stage.230
230. MSFC Saturn V Prog. Off., Saturn V QPR, April-June
1965, p. 15.
S&ID activity during April included installation and
checkout of electro-mechanical mockup systems, beginning vertical assembly
of S-II-F, and the first test to ultimate load on the S-II-S/D. In April
also, NASA modified a Boeing contract to provide engineering services and
instrumentation for the Saturn V dynamic test program.
May
On May 4 the S-IVB battleship stage successfully performed
a hot-gimbal, full-duration firing at SACTO to conclude the Saturn IB battleship
hot-firing test phase.231 The following day S-IVB-201 arrived
at Courtland, California, aboard the barge Orion. There workmen
unloaded it and placed it on the S-IVB transporter for the remainder of
its journey to SACTO. The next day, May 6, S-IVB-201 arrived at SACTO,
and preparations began immediately for positioning it in the Beta III test
stand.
231. NAA S&ID, S-II Stage MPR, Apr. 1965,
p. 36.
|
233
233. S-IVB-201 en route to
Courtland, California, aboard
the Orion |
On May 7 at Santa Susana there was a successful
10-second cluster firing of the S-II battleship after two previous unsuccessful
attempts.232
232. MSFC Saturn V Prog. Off., Saturn V QPR, Apr.-June
1965, p. 21; MSFC Sat. V Prog. Off., "Saturn V Weekly Report No. 18,"
May 10, 1965.
Douglas on May 10 delivered the tenth and last Saturn I S-IV
stage (S-IV-10) to KSC aboard the Pregnant Guppy aircraft.
MSFC submitted the procurement plan for nine additional
Saturn V S-IVB stages to the NASA Office of Manned Space Flight (OMSF)
on May 17 for approval. |
|
234 |
234. S-IVB production
sequence
235. S-II stage |
Final period of countdown for the SA-8 launch started
on the afternoon of May 24 and, except for a scheduled 35-minute hold,
continued uninterrupted to liftoff. Liftoff occurred the next day, May
25, as SA-8 flew the ninth successful Saturn I flight. SA-8 placed in orbit
Pegasus B.233
233. MSFC Saturn V Prog. Off., Saturn V QPR, Apr.-June
1965, p. 15.
Workmen on May 25 successfully completed vertical assembly
of the S-II-T, in progress at Seal Beach since February. On May 26, the
first stage S-I-10, for the tenth and last Saturn I launch vehicle left
Michoud on the barge Promise for KSC.
During May MSFC and Rocketdyne completed negotiations
for conversion of the J-2 contract to an incentive type.234
Also in May S&ID structural assembly of the S-II-2 flight stage began
at Seal Beach. Technicians at SACTO began conversion of the S-IVB battleship
from the Saturn IB to the Saturn V configuration.
234. MSFC Saturn Flight Evaluation Working Group, Results
of the Ninth Saturn I Launch Vehicle Test Flight SA-8 (MPR-SAT-FE-66-10),
June 13, 1966, pp. 1-6, 8-9, 14-15, 19-30, and 91-97; William M. Bland,
Jr., Chief, Checkout and Test Division, MSC, to NASA Headquarters, Attn:
R. R. Gilruth, et al, teletype, subj: "Apollo Mission A-104 (SA-8)
Flight Report," May 28, 1965.
|
235
236
|
237 |
236. Launch of SA-8 from
pad 37B at KSC
237. Rocketdyne technicians
checking out a J-2 engine |
S-IU-10, final instrument unit for the Saturn I vehicles,
arrived at KSC from MSFC on June 1, a day before KSC technicians erected
the S-I-10 on Launch Complex 37B.
June
On June 8 the launch support crew at KSC erected the S-IV-10
atop the S-I stage on Launch Complex 37B. KSC technicians on June 9 erected
the S-IU-10 on the SA-10 vehicle and began connecting umbilicals of the
launch support equipment.
CCSD shipped the S-IB-2 stage on June 12 from Michoud
to MSFC.
After arriving at Seal Beach from SACTO on the barge Orion,
the S-IVB-500F stage on June 13 went aboard the USNS Point Barrow
for its trip to KSC via the Panama Canal. |
|
238 |
238. Point Barrow, carrier
for S-IVB-500F stage
239. Launch complex 34
gantry at KSC |
MSFC workmen completed structural assembly of S-IU-500V
on June 14.235
235. L. F. Belew, Mgr., Engine Prog. Off., MSFC, paper,
"Apollo Vehicle Propulsion Systems," AIAA Annual Meeting, July 26-29, 1966,
Paper 65-303; Engine Prog. Off., Semiannual Progress Report, July-December
1965, p. 30.
The S-IB-2 stage arrived at MSFC's Huntsville dock on June
19 from where Chrysler and MSFC personnel moved it to the static test tower
in preparation for a series of acceptance firings. The S-IU-200F/500F left
MSFC on this date en route to Michoud to await reshipment to KSC. At KSC
it would be used in facilities checkout of Launch Complex 34. On June 19
at SACTO test personnel attempted the first Saturn V development firing
of the S-IVB battleship; the test ended after several seconds because of
an automatic cutoff.236
236. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 42.
|
239 |
The Apollo BP-9 service module and service
module adapter, modified by MSFC to serve as a shroud for the Pegasus C
experiment, arrived at KSC on June 21. Meanwhile at KSC, to avoid delay
of the SA-10 launch and also delay of planned Launch Complex 37B modification,
NASA shifted the launch to July 30, ahead of the Gemini 5 launch.237
237. MSFC Saturn V Prog. Off., Saturn V QPR, Apr.-June
1965, p. 21.
In a last captive-firing condition test at MSFC S-IC-S on
June 21 withstood 140 percent of the design load.238
238. Rocco A. Petrone, Dir., Plans, Programs, and Resources,
KSC, to Col. Lee B. James Saturn I/IB Program Mgr., MSFC, teletype, subj:
"Possible Interference of Scheduled Launch Date of SA-10 with that of GT-5,"
June 10, 1965; Kurt H. Debus, Dir., KSC, to Dr. George E. Mueller, Assoc.
Adm., Office of Manned Space Flight, subj: "Possible Interface of Launch
Schedules," June 11, 1965; Maj. Gen. Samuel C. Phillips, Dir. Apollo Program
Office, NASA, to Dr. Wernher von Braun, Dir. MSFC, subj: "Reschedule of
SA-10 Launch," June 21, 1965.
The Fairchild Hiller Corporation shipped the third meteoroid
detection satellite, Pegasus C, to KSC on June 22 aboard the Pregnant Guppy
aircraft. |
240
240. Pegasus with partial
deployment of wings
241. Opening of locks at
MTF |
After investigating ways to reduce the complexity
of the Saturn/Apollo onboard communications and tracking systems, MSFC
on June 28 recommended, and NASA approved, deletion of the MISTRAM transponder
and use of the more reliable AZUSA "C." Both were not required for program
success.239 On this date also the S-II stage simulator became
the first "space-age" hardware to pass through the Mississippi Test Operations
lock and into the site's seven and one-half mile canal system.
239. MSFC P&VE Lab., MPR, June 1-30, 1965,
p. 49.
The Point Barrow arrived at KSC on June 29 with the
S-IVB-500F. Arriving at KSC on June 29 was the last boilerplate version
of the Apollo spacecraft command module. It arrived from MSFC along with
the launch escape system. |
241 |
During June MSFC began contracting negotiations
with Rocketdyne for the 22 remaining engines needed for the 12 Saturn IB
vehicles. S&ID technicians at Seal Beach began assembly of S-II-3,
the third Saturn V flight stage.
July
A July 1 "third firing" of the Saturn IVB battleship stage
(Saturn V configuration) at SACTO resulted in an explosion and fire that
damaged wiring and instrumentation.240
240. Maj. Gen. Samuel C. Phillips, Dir., Apollo Program,
NASA to E. Betram, KSC, et al, teletype, subj: "AFETR CW Radar Standardization,
June 28, 1965; and Azusa/Mistram," June 28, 1965.
On July 2 NASA at KSC awarded a $6,745,000 construction contract
to adapt Launch Complex 37 for Saturn IB. Also at KSC, following completion
of premating systems checks and panel deployment checks, technicians on
July 6 attached Pegasus C to the S-IU-10 instrument unit. They then positioned
BP-9 as the shroud for the satellite. A July 6 Saturn V milestone occurred
at Seal Beach, California, as workmen began vertical buildup of the S-II-1.241
241. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 26; Saturn V Prog. Off., "Saturn V Weekly Report, No. 26,"
July 7, 1965.
After a suggestion by NASA Administrator James E. Webb, the
name of the Mississippi Test Operations was officially changed to Mississippi
Test Facility (MTF).
A faulty signal from the engine pressure switch on July
8 automatically ended a first attempt to static fire S-IB-2 in the S-IB
test stand at MSFC. The test, conducted by Chrysler personnel, lasted only
three seconds. But the following day the S-IB-2 stage successfully performed
a short-duration 35-second captive firing in the stand.242 On
July 12 component assembly of the S-IU-500ST started at ME Lab. A 27-second
S-II battleship firing occurred at Santa Susana Field Laboratory (SSFL)
on July 13; this was the longest firing to date of the S-II program.243
242. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 23.
243. MSFC Test Lab., Hist. Report, Jan. 1-Dec. 31,
1965, pp. 1-2.
|
242
242. S-IB static test
Huntsville
243. Saturn SA-10 during
countdown demonstration test |
The S-IB-2 stage successfully completed its
series of static tests at MSFC with a 2.5-minute full-duration test on
July 20.244
244. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 18.
In the Saturn V program, on July 20 technicians at SSFL successfully
accomplished a 150-second firing of the S-II battleship. The KSC launch
crew successfully performed the countdown demonstration test for SA-10
on July 27. Final phase of countdown for the SA-10 launch was under way
at 9:25 pm est on July 29 and continued to liftoff without any technical
holds. On July 30 SA-10, the final flight test of the Saturn I program,
performed excellently. The launch vehicle inserted its dual payload of
Pegasus C and BP-9 into an orbital trajectory. This SA-10 flight concluded
NASA's Saturn I program.245
245. MSFC Test Lab., Hist. Report, Jan. 1-Dec. 31,
1965, pp. 1-2.
The second Saturn IB booster (S-IB-2) left MSFC's Huntsville
port aboard the barge Palaemon on its return trip to Michoud on
July 30.
A component malfunction in pneumatic console A at SACTO
prematurely ended the first attempt to static fire S-IVB-201. But stage
propellant loading and the automatic countdown sequence proceeded satisfactorily
to the point of cutoff in this July 21 static firing.246
246. MSFC Saturn Flight Evaluation Working Group, Results
of the Tenth Saturn I Launch Vehicle Test Flight SA-10, July 14, 1966,
(MPR-SAT-FE-66-11), pp. 5-9.
During July in support of the Saturn IB and V programs Rocketdyne
completed the flight rating tests of the 200K J-2 engine at SSFL. Also
in July, Rocketdyne initiated a development program to uprate the J-2 engine
thrust capability from 200K to 230K.247
247. DAC, Saturn S-IVB Monthly TPR, July 1965,
p. 48.
|
243
244
|
245 |
244. Launch of SA-10 from
pad 37B, KSC
245. Technicians checking
Rocketdyne built J-2 engines
on S-II stage |
August
On August 2 MSFC personnel conducted the first successful
ignition test of the MSFC S-IVB battleship. It lasted for 2.1 seconds.
This first firing of the MSFC S-IVB battleship completed activation of
the J-2/S-IVB test stand at MSFC.248
248. Belew, AIAA Paper 65-303, pp. 12-14; MSFC Engine
Prog. Off., Semiannual Progress Report, July-December 1965, pp.
21-23.
The first full-duration run of S-IC-T occurred at MSFC on
August 5. The firing lasted 143.6 seconds.249
249. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, pp. 26-27; MSFC Test Lab., Hist. Report, Jan. 1-Dec. 31, 1965,
Addendum, pp. 1-3.
|
246
246. S-IC static firing |
The S-IVB-201 stage successfully performed
a full-duration firing of 452 seconds at SACTO on August 8. The test was
computer-controlled throughout, marking the first use of a fully automatic
system for performing a complete checkout, propellant loading, and static
firing of a vehicle stage.250
250. MSFC Test Lab., Hist. Report, Jan. 1-Dec. 31,
1965, pp. 7-8.
|
|
247 |
247. Computer room during
S-IVB-201 firing at Sacramento |
On August 9 Chrysler shipped the first Saturn IB flight
booster, S-IB-1, to KSC. The stage would be used in launch facilities checkout
and then readied for flight.
In the Saturn V program, on August 9 S&ID at SSFL
accomplished a full-duration S-II battleship cluster firing; it terminated
manually after 385.6 seconds.251 And the structure of the S-IU-200S/500S
on August 13 withstood 140 percent load limit at MSFC, proving its structural
integrity.252 Meanwhile, Boeing workmen at Michoud began final
assembly of the S-IC-4 thrust structure.
251. NASA Hist. Off., Astronautics and Aeronautics,
1965, Chronology on Science, Technology, and Policy, SP-4006, p. 373.
Hereafter cited as NASA Hist. Off., Astronautics and Aeronautics, 1965.
252. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 18.
The S-IB-1 and S-IU-200F/500F arrived at KSC on August 14
aboard the barge Promise from Michoud. This cargo was the first
barged through the new Port Canaveral locks.
The first two-burn full-duration firing of the S-IVB battleship
lasted 170 and 320 seconds, respectively, at SACTO on August 17.253
253. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 40.
|
248
248. S-II battleship cluster
firing at SSFL |
| At KSC workmen transported the S-IB-1 stage
to Launch Complex 34 and erected it on the pad on August 18. On this same
day workmen also completed erection of the S-IVB-500F stage and the S-IU-200F/500F
on Launch Complex 34, using the S-IB-1 stage as a spacer, and began vehicle
checkout of the Saturn IB launch facilities with propellant tankings to
verify the facility LOX and liquid hydrogen loading systems. Also on August
18 Chrysler personnel at Michoud completed pre-static checkout of S-IB-3.
Conclusion of the Saturn V S-IVB battleship test program
occurred at SACTO on August 20 with a two-burn test for 170 and 360 seconds.254
Meanwhile, at MSFC on this date technicians completed S-IU-500V assembly
and delivered it to test contractor.
254. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 26; MSFC Saturn V Prog. Off., "Saturn V Weekly Report No.
32," Aug. 23, 1965.
On August 29 MTF operations began with installation of S-II
stage simulator into test stand A-2 for facility checkout. |
249
249. S-II A-2 test stand,
Mississippi Test Facility
250. S-IVB-201 being hoisted
on the Steel Executive |
September
The S-IVB-202 stage arrived at SACTO from Huntington Beach
on September 1. The following day Douglas technicians installed the stage
on the SACTO Beta III test stand and continued stage modification not accomplished
at Huntington Beach because of parts shortages and design changes.255
Then on September 3 Douglas transported the S-IVB-201 to the Courtland
dock, loaded it on board the Orion, and shipped it to Richmond,
California, where it would be loaded on the ocean freighter Steel Executive
for the rest of its journey to KSC.256
255. MSFC Saturn V Prog. Off., Saturn V QPR, July-Sept.
1965, p. 26; MSFC Saturn V Prog. Off., "Saturn V Weekly Report No.
32," Aug. 23, 1965.
256. DAC, Saturn S-IVB Monthly TPR, Sept. 1965,
p. 38.
|
250 |
| On September 8 workmen at SACTO removed the
S-IVB battleship from the Beta I stand and shipped it to Tullahoma, Tennessee,
for engine environmental testing. |
|
251 |
251. Altitude simulation
test facility at Tullahoma,
Tennessee |
Hurricane Betsy entered the Michoud area about 8 pm on
September 9 and left severe roof and building damage at Michoud. It also
washed the NASA barge Promise upon the levee, inflicting damage
to the barge in the amount of $89,138. The NASA barge Palaemon,
with the S-IB-3 stage as cargo, weathered Hurricane Betsy near Baton Rouge,
Louisiana, without damage during the first day of its journey from Michoud
to MSFC in Huntsville. |
|
|
|
252. Damage at Michoud by
Hurricane Betsy
253. NASA barge Promise
upon levee after Hurricane
Betsy
254. Hurricane Betsy leaves
Promise on levee
255. Aftermath of Hurricane
Betsy at Michoud |
IBM on September 9 delivered to NASA the flight launch
vehicle digital computer and launch vehicle data adapter (LVDC/LVDA) for
the AS-201 vehicle.257
257. DAC, Saturn S-IVB Monthly TPR, Sept. 1965,
p. 38.
The upper stage testing in the Saturn IB dynamic test program
ended at MSFC on September 11. The S-IVB battleship at MSFC fired for 400
seconds on September 15, a full-duration test.258 On September
16 the S-IB-3 arrived at MSFC where Chrysler test engineers would static
fire the stage in MSFC's S-IB test stand before returning it to Michoud.
258. MSFC Saturn I/IB Prog. Off.,Saturn I/IB Prog.
Report, Oct. 1, 1964-Mar. 31, 1965, p. 1; IBM, Saturn Instrument
Unit Mission Monthly Progress Report for September, pp. 1, 7, 22, and
30.
The S-IVB-201 arrived at KSC aboard the Steel Executive
September 19; workmen unloaded the stage and moved it to the special assembly
building for receiving inspection.
On September 29 the S-II-S/D ruptured and disintegrated
during a structural loading test at Seal Beach. The failure occurred at
144 percent of limit load on the aft skirt. This failure necessitated redirection
of the S-II program by substitution of the S-II-T as a dynamic test vehicle
following static testing at MTF.259
259. MSFC Test Lab., Addendum to Test Lab. Hist. Report,
Jan. 1-Dec. 31, 1965, pp. 1-3.
|
255
256
256. S-IB-200D at MSFC
dynamic test stand |
Workmen at Seal Beach completed manufacture
of the S-II-T stage on September 30. Meanwhile, on this date IBM at Huntsville
completed fabrication of the S-IU-200S/500S-II.260
260. MSFC Saturn V Prog. Off., Saturn V QPR, Oct.-Dec.
1965, pp. 15 and 17; NAA S&ID, S-II Stage MPR, Sept. 1965,
p. 41.
|
|
257 |
257. S-IU-200/500S on
fabrication stand No. 1
258. Loading S-II-T on AKD
Point Barrow |
During September NASA added to the Boeing contract (NAS8-5608
Schedule II) $4.5 million to provide services in connection with systems
engineering and integration of mechanical GSE.
October
Workmen at KSC on October 1 mated the S-IVB flight stage
for AS-201 (S-IVB-201) to the S-IB-1 stage on Launch Complex 34.261
Also on October 1 NASA approved a two-year incentive contract with Pratt
& Whitney for follow-on RL10 engine research and development effective
this date. The contract covered qualification of RL10-A-3-3 (uprated version)
for Centaur application and continued flight support. In the Saturn V program
on October 1 the S-II-T, S-II all-systems stage, left Seal Beach on the
Point Barrow bound for MTF.
261. MSFC Saturn V Prog. Off., Saturn V QPR, Oct.-Dec.
1965, p. 34.
|
258 |
| On October 6 workmen at Michoud completed
assembly of the S-IVB-4 stage, and the stage entered pre-static checkout.
The first S-IC-T firing in automatic configuration occurred
at MSFC on October 8 for a scheduled duration of approximately 45 seconds.262
On October 13 the S-IC-D arrived at MSFC's Saturn V dock after leaving
Michoud dock aboard the barge Poseidon October 6, the Poseidon's
first trip. Two days later technicians at MSFC began Saturn V dynamic testing
of the S-IU-200D/500D.
262. MSFC Saturn Flight Evaluation Working Group, Results
of the First Saturn IB Launch Vehicle Test Flight AS-201, (MPR-SAT-FE-66-8),
May 6, 1966, p. 13.
|
|
259
260
|
259. S-IC-T static test
firing
260. S-IC-D being unloaded
from barge Poseidon
261. S-II-T arriving at S-II-A2
stand at MTF
262. Installation of S-II-T
in MTF test stand A2 |
The S-II-T, first "live" launch vehicle stage at MTF,
arrived October 17 for start of stage all-systems testing. S&ID personnel
at MTF placed S-II-T into test stand A-2 on October 19.263 The
S-IU-201 arrived at KSC on October 20 aboard the Palaemon; workmen
unloaded it and took it to Hanger AF for prelaunch checkout. Five days
later technicians at KSC erected the S-IU-201 atop the S-IVB-201 stage
on Launch Complex 34. That same day, October 25, Apollo command module
009, part of the payload for the AS-201 vehicle, arrived at KSC and entered
checkout.
263. MSFC Test Lab., Hist. Report, Jan. 1-Dec. 31,
1965, pp. 8-9. N. C. Milwee, Manufacturing Engineering Lab., MSFC,
"Quarterly Report, July-Sept. 1965," (draft)
Douglas technicians on October 26 completed the S-IVB-202
pre-static firing checkout at SACTO. On this date S-IB-3 successfully performed
a 2.5-minute static firing in the S-IB static test stand at MSFC in Huntsville.264
264. MSFC Saturn V Prog. Off., Saturn V QPR, Oct.-Dec.
1965, p. 17.
On October 28 Rocketdyne delivered to Chrysler at Michoud
the first two H-1 engines uprated from 200K to 205K. Eight of the uprated
engines would add about 40,000 pounds thrust to the S-IB stage and increase
the total thrust of the stage to 1,640,000 pounds.265
265. Systems Static Test Branch, CCSD, Saturn S-IB
Stage Final Static Test Report, Stage S-IB-3, pp. 3-5.
Difficulties experienced with the stage electric power system
at SACTO terminated the first S-IVB-202 acceptance firing attempt on October
29.266 Also on October 29, the S-IVB stage contractor shipped
S-IVB-203 to SACTO.
266. MSFC P&VE Lab., MPR, Oct. 1-31, 1965,
p. 19; MSFC Press Release No. 65-259, Oct. 28, 1965.
During October construction of the Launch Complex 39 pad
A ended at KSC.
November
NASA on November 1 increased Chrysler's contract NAS8-4016
some $18,909,000 to cover additional systems engineering. In the Saturn
V program on this date the Propulsion and Vehicle Engineering (P&VE)
Laboratory at MSFC began the first series of S-IU-200S/500S-II tests.
On November 2 the second S-IVB-202 acceptance firing attempt
ended at SACTO after 0.41 seconds of mainstage because of a component malfunction
in the J-2 engine combustion stability monitoring system.267
SACTO activated test stand Beta I on November 3 with installation of S-IVB-203.
267. DAC, Saturn S-IVB Monthly TPR, Oct. 1965,
p. 33.
The final scheduled test of the S-II common bulkhead test
tank (CBTT) ended at Santa Susana on November 6. The CBTT was tested to
1.4 times the limit burst pressure. Completion of these tests, which verified
the integrity of the common bulkhead, the liquid hydrogen tank, and the
forward skirt, was a major milestone in the S-II stage program.268
268. DAC, Saturn S-IVB Monthly TPR, Nov. 1965,
pp. 39-40.
|
261
262
263
264
263. S-IVB-202 installed in
test stand Beta 3 at SACTO
264. H-1 engine |
On November 8 the Saturn IB stage S-IB-3
arrived at Michoud from Huntsville to undergo post-static checkout and
modification. The next day the S-IVB-202 stage performed a long-duration
(307 seconds mainstage) acceptance firing at SACTO; a malfunctioning liquid
hydrogen mass sensing unit in the propellant utilization (PU) subsystem
prevented completion of the test to full duration.269 Pre-static
checkout of S-IB-4, completed at Michoud on this date, revealed no significant
problems.
269. MSFC Saturn V Prog. Off., Saturn V QPR, Oct.-Dec.
1965, p. 14.
Workmen at Seal Beach completed all S-II-1 major subassemblies
on November 25 with assembly of the aft LOX bulkhead.
There was a November 30 automatic LOX loading test of
the S-IB-1 at KSC to verify the automatic LOX loading and replenish systems
and the LOX drain systems. The stage withstood a LOX load of 100 percent;
during the loading all stage systems functioned normally.270
On this date Chrysler technicians completed assembly of S-IB-5 and moved
it into the checkout station for pre-static checkout.
270. DAC, Saturn S-IVB Monthly TPR, Nov. 1965,
pp. 39-40.
|
265. S-II common bulkhead
test tank (CBTT)
265
|
In November NASA announced that the J-2 engine
contract would be amended to add 48 engines. NASA in addition asked Rocketdyne
to provide 52 additional J-2 engines for delivery in 1967 and 1968.271
November also saw the completion at Seal Beach of all engine deliveries
for S-II-1 and S-II-2.
271. MSFC Saturn Flight Evaluation Working Group, Results
of the First Saturn IB Launch Vehicle Test Flight AS-201, (MPR-SAT-FE-66-8),
May 6, 1966, p. 13; MSFC P&VE Lab., MPR, Dec. 1-31, 1965, Supplement,
pp. 1-3.
|
|
266 |
266. Major components of
J-2 engine |
| 1.
Oxidizer Turbopump |
9.
Exhaust Manifold |
| 2.
Propellant Utilization Valve |
10.
Anti-Flood Check Valve |
| 3.
High-Pressure Oxidizer Duct |
11.
Auxiliary Flight Instrumentation Package |
| 4.
Electrical Control Package |
12.
Customer Connect Lines (Electrical) |
| 5.
Primary Flight Instrumentation Package |
13.
Accessory Drive Pad |
| 6.
High-Pressure Fuel Duct |
14.
Gaseous Hydrogen Start Bottle |
| 7.
Fuel Manifold |
15.
Customer Connect Lines (Pneumatic) |
| 8.
Thrust Chamber |
16.
Oxidizer Inlet Duct |
|
|
December
On December 1 the S-IVB-202 stage successfully achieved all
test objectives during its full-duration (463.8 seconds mainstage) acceptance
firing at SACTO. Cutoff occurred automatically when the PU system indicated
less than one percent LOX.272
272. Belew, AIAA Paper 65-303; MSFC Engine Prog. Off.,
Semiannual Prog. Report, July-Dec. 1965, p. 30.
MSFC and Boeing on December 3 negotiated a supplemental agreement
establishing Schedule III (Saturn V launch operations support) effective
December 31, 1965. In the Saturn V program on December 16, the final captive
test firing of the S-IC-T in original automatic configuration occurred
at MSFC.273
273. DAC, Saturn S-IVB Monthly TPR, Dec. 1965,
pp. 35-36 and 41.
The S-IB-4 stage departed Michoud on December 7 aboard the
NASA barge Palaemon for the MSFC test site at Huntsville. MSFC workmen
on December 14 unloaded the stage from the Palaemon, moved it to
the MSFC static test tower, and completed its installation in the tower.
The following day, also in the Saturn IB program, Douglas completed Phase
I of the S-IVB-204 pre-static checkout and successfully performed a simulated
flight test before beginning preparations for shipping the stage to SACTO.
Qualification testing of the J-2 engine at the 200K level,
which began on December 2, ended successfully at SSFL on December 17.274
274. MSFC Press Release No. 66-4 and No. 66-8, Jan. 7,
1966.
Technicians at KSC erected Apollo spacecraft 009 atop the
AS-201 launch vehicle at Launch Complex 34 on December 26.275
275. MSFC Engine Prog. Off., Semiannual Prog. Report,
July-Dec. 1965, p. 21.
|
|
267 |
267. Apollo spacecraft |
On December 29 MSFC forwarded to NASA Headquarters for
approval a supplement providing for conversion of the Boeing S-IC stage
contract to cost-plus-incentive-fee; the cost-effective date of this change
was July 2.
During December MSFC initiated negotiations with Rocketdyne
for a combined J-2 research and development contract NAS7-190 from a CPFF
to a CPIF contract. In December preliminary data from the three Pegasus
flights indicated that the Apollo spacecraft structure as designed would
be adequate to resist meteoroid penetration.276 Two F-1 turbopump
explosions occurred, one at SSFL and one at Edwards.
276. MSFC Saturn V Prog. Off., Saturn V QPR, Oct.
1-Dec. 31, 1965, p. 34; MSFC Saturn V Flight Evaluation Working Group,
Results of the First Saturn IB Launch Vehicle Test Flight AS-201
(MPR-SAT-FE-66-8), p. 13.
|
|