-
SP-4011 Skylab: A
Chronology
-
-
- THE KEY
EVENTS
-
-
-
-
-
- [xi] 1959
-
-
- 20 February: NASA officials outlined the
long-range objectives of the agency's space program to a Senate
committee. The objectives included a multimanned orbital space
station.
-
- 8 June: In a Project Horizon report,
Wernher von Braun advanced a theory for using a spent booster
stage as a space station's basic structure.
-
-
- 1961
-
-
- 5-6 January: McDonnell Aircraft
Corporation proposed a one-man space station consisting of a
Mercury spacecraft and a cylindrical space laboratory capable of a
14-day mission in a shirt- sleeve environment.
-
-
- 1962
-
-
- April: MSC designers and planners prepared
a preliminary document that outlined areas of investigation for a
space station.
-
- 17 October: Joseph F. Shea, OMSF,
solicited suggestions from each of the NASA Hq Program Offices and
the NASA Centers on potential uses and requirements for a manned
space station. Such ideas, he said, would help determine whether
adequate justification existed for such a space laboratory.
-
-
- 1963
-
-
- 1 June: MSC announced two space station
study contracts for a 24-man orbital laboratory to be designed for
a useful orbital lifetime of five years.
-
-
- 1965
-
-
- 6-10 August: NASA's Associate
Administrator for Manned Space Flight advised Center Directors of
establishment of a Saturn/Apollo Applications Office within
OMSF.
-
- 20 August: MSFC designers began serious
investigation of an S-IVB Orbital Workshop involving in orbit
conversion of a spent S-IVB stage to a habitable shelter for
extended manned utilization.
-
- 10 September: The Apollo Extension System
was redesignated the Apollo Applications Program.
-
- 13 September: MSC, MSFC, and KSC were
officially informed of the changed guidelines for Center
management roles.
-
-
- 1966
-
-
- 28 January: Potential benefits of the
Apollo Applications Program were summarized by George E.
Mueller.
-
- January: Douglas Aircraft Company
submitted a summary report to LaRC covering the activities of
three phases of the Manned Orbital Research Laboratory conducted
from June 1963 to February 1966.
-
- [xii] 21 March: The
Manned Space Flight Experiments Board was created by agreement
between NASA and the Department of Defense.
-
- 1 April: MSC presented a request for
proposals to Douglas, Grumman, and McDonnell for definition
studies on the Saturn S-IVB spent-stage experiment support module
(SSESM).
-
- 6 May: Astronauts voiced concern over the
purposes and proposed work statement for the SSESM, noting a
number of operational and safety concerns connected with purging
the stage's hydrogen tank to create a habitable structure in
space.
-
- 11 July: NASA Hq officials made several
significant AAP decisions concerning the roles of MSFC and
MSC.
-
- 25 July: The Orbital Workshop was approved
as an experiment for flight on AS-209.
-
- 26 July: Full responsibility for AAP
missions was assigned to the Office of Manned Space Flight, NASA
Hq.
-
- 13-15 August: Agreement was reached on the
respective roles of MSC and MSFC in development and operations of
future manned space flight hardware.
-
- 19 August: NASA announced selection of
McDonnell to manufacture the airlock module for AAP.
-
- 30 December: Mission objectives for AAP-l
and AAP-2 flights were outlined by NASA Hq.
-
-
- 1967
-
-
- 26 January: NASA announced plans to use a
cluster configuration for AAP flights.
-
- 26 July: NASA selected Martin Marietta
Corporation as contractor for payload integration of experiments
and experiments support equipment.
-
- 2 August: NASA terminated all activity
associated with the lunar mapping and survey system.
-
-
- 1968
-
-
- 2 February: Key check points were
established for AAP to ensure sufficient management visibility of
the program status.
-
- 20 July: The Post Apollo Advisory
Committee issued its report which confirmed the basic objectives
of AAP and played a deciding role in its later evolution.
-
-
- 1969
-
-
- 4 March: An AAP baseline configuration
review was held at NASA Hq.
-
- 2 May: An AAP Software Board was
established.
-
- 21 May: Choice of a Saturn IB "wet"
Workshop vs. a Saturn V "dry" Workshop was the major subject
discussed at a Manned Space Flight Management Council
meeting.
-
- 23 May: MSFC Director Wernher von Braun
responded to George E. Mueller's request for recommendations from
the field Centers on the "wet" vs. "dry" Workshop issue, saying he
preferred the "dry" Workshop and giving his reasons.
-
- 18 July: NASA Administrator Thomas O.
Paine approved the shift from a "wet" to a "dry'' Workshop.
-
- 22 July: AAP Director William C. Schneider
directed the three manned space flight Centers to implement the
necessary changes to effect the "dry" Workshop program.
-
- 8 August: MSFC definitized the contract
with McDonnell Douglas for two Orbital Workshops for AAP.
-
- 16 September: NASA announced the AAP
change from "wet" to "dry" Workshop substantially improved the
probability of mission success and crew safety.
-
- 22 October: The AAP Director approved
changes in the Orbital Workshop at a meeting at MSFC.
-
-
- 1970
-
-
- 2 January: MSFC shipped a test version of
the Saturn S-IVB stage to McDonnell Douglas to be converted into
an Orbital Workshop test article.
-
- [xiii] 17 February:
NASA announced that AAP had been redesignated the Skylab
Program
-
- 18 March: An interface panel organization
was established within the NASA Skylab Program for defining,
controlling, and resolving inter-Center problems.
-
- 4 May: A system flexibility study was
conducted of systems and subsystems in the Skylab cluster to
achieve maximum flexibility in case of a malfunction.
-
- 15 May: NASA announced that both the
Skylab Saturn V and Saturn IB launches would be from Launch
Complex 39 at KSC.
-
- 26 May: The Apollo telescope mount
critical design review was completed at MSFC and final approval
given the ATM design.
-
- 10-14 August: A critical design review for
the airlock module was held at McDonnell Douglas.
-
- 24-27 August: A critical design review of
Skylab's multiple docking adapter was completed at Martin
Marietta, Denver.
-
- 14-18 September: An Orbital Workshop
critical design review was conducted at McDonnell Douglas,
Huntington Beach, California.
-
- 21 September: A Saturn Workshop crew
station review began at MSFC with Government and industry
engineers monitoring the progress of nine astronauts as they
"walked through" many of the Workshop tasks.
-
- 16-20 November: An EVA critical design
review was held at the MSFC mockup area and neutral buoyancy
simulator with 10 astronauts participating.
-
-
- 1971
-
-
- 12 February: Acoustic testing of the
Orbital Workshop dynamic test article was completed at MSC.
-
- 15 December: An MSFC-MSC agreement was
approved detailing responsibilities for Skylab flight crew
training in the neutral buoyancy simulator at MSFC.
-
- December: The Skylab Program was reviewed
by a Skylab midterm task team.
-
-
- 1972
-
-
- 11-12 January: The Manned Space l light
Management Council agreed to retain the 30 April 1973
launch-readiness date.
-
- 19 January: Prime crewmen were named for
the three Skylab missions.
-
- 7 March: The Skylab rescue mission was a
definite NASA commitment.
-
- 21 June: A CSM design certification review
board met at MSC and concurred in accepting the CSM design for
Skylab.
-
- 17 July: A Skylab vibration and acoustic
test program which began at MSC in January 1971 was
completed.
-
- 29 August: After completion of 28 days of
the Skylab medical experiments altitude tests at MSC, it was
decided to continue the planned 56-day test to completion.
-
- 6-7 September. A special ceremony marked
completion of the Orbital Workshop prior to its readiness for
shipment from Huntington Beach to KSC.
-
- 19 October: A Skylab cluster systems
design certification review was conducted at MSFC.
-
- 21 November: NASA Hq defined the review
procedure and readiness requirements for the flight readiness
review which would be conducted prior to each Skylab
mission.
-
- 30 November: Skylab cost savings were
achieved by increasing payload weights in some instances.
-
-
- 1973
-
-
- 29-30 January: The airlock, multiple
docking adapter, and Apollo telescope mount flight units were
mated to the lunar vehicle.
-
- 27 February: Skylab 2 was moved from the
Vehicle Assembly Building to Launch Pad 39.
-
- 5 April: Planning dates for the four
Skylab launches were officially confirmed by NASA.
-
- 17-20 April: A flight readiness review was
held at KSC, followed by an announcement of "ready to go" for
Skylab I on 14 May and Skylab 2 on 15 May.
-
- [xiv] 14 May: Skylab I
was launched from KSC. Deployment of the Workshop solar array and
the meteoroid shield was not successful, requiring a postponement
of the Skylab 2 launch.
-
- 23-24 May: The design certification review
board determined that a "Skylab Parasol," deployed through the
scientific airlock, would be the prime method of improvising a
thermal shield for the Workshop.
-
- May: Skylab 2 was launched from KSC and
rendezvoused with Skylab I during the fifth revolution. Damage to
Skylab I was reported to the ground.
-
- 26 May: The crew completed the task of
deploying the Skylab parasol, and the Workshop temperature started
to drop.
-
- 7 June: Two astronauts performed an EVA
and successfully freed the undeployed solar array, after which it
was fully deployed.
-
- 22 June: The Skylab 2 command module
splashed down in the Pacific Ocean following a successful 28-day
mission.
-
- 28 July: Skylab 3 was launched from KSC
and began its mission, ending with a landing in the Pacific Ocean
on 25 September.
-
- 13 August: A decision was made to delete
the Skylab Saturn V Orbital Workshop capability effective 15
August.
-
- 30 August: Guidelines were issued by NASA
for release, disposition, and storage of all unneeded Skylab
Program equipment.
-
- 16 November: Skylab 4 was launched from
KSC for a planned duration mission of 56 days with an option of
extending it to 84 days. The command module and crew splashed down
in the Pacific Ocean 8 February 1974, 84 days 1 hour 15 minutes 31
seconds after liftoff.

