Year
.
1969
104 500 a
--- b
42 275 c
1970
--- d
---
--- e
1971
--- f
---
25 659 g
1972
--- h
---
39 582 g
1973
65 900 g
65 900
--- i
1974
74 000 j
74 000 j
13 000 k
1975
32 500 l
--- m
--- n
a Includes $69 100 000 from the Apollo request and $35 400 000 from Apollo applications.
b Of the $2 038 800 000 Apollo request, $2 025 000 000 was authorized; the chronological history does riot indicate from which Apollo line item(s) the $13 800 000 was deducted. Of the $439 600 000 request for Apollo applications, $253 200 000 was authorized; the chronological history does not indicate from which Apollo applications line item(s) the $186 400 000 was deducted,
c From the Apollo budget. $52 645 000 was programmed for Apollo applications space vehicles, including Saturn 113; the FY 1971 budget estimate does not indicate the exact amount programmed for launch vehicles.
d $138 400 000 was requested for Apollo application space vehicles, including Saturn IB; the FY 1970 budget estimate does not indicate the exact amount requested for launch vehicles.
e $63 330 000 was programmed for Skylab space vehicles, including Saturn 113; the FY 1972 budget estimate does not indicate the exact amount programmed for launch vehicles.
f $89 600 000 was requested for Skylab space vehicles, including Saturn M; the FY 1971 budget estimate does not indicate the exact amount requested for launch vehicles.
g From the Skylab budget/request.
h $194 000 000 was requested for Skylab space vehicles, including Saturn M; the FY 1972 budget estimate does not indicate the exact amount requested for launch vehicles, the FY 1975 budget estimate does not indicate how Skylab funds were programmed in FY 1973, it was estimated in the FY 1974 budget estimate that $65 300 000 would be programmed in FY 1973 for Saturn 113.
j Includes $64 500 000 for Skylab and $9 500 000 for ASTP.
k From the ASTP budget. The FY 1975 and 1976 budget estimates do not indicate flow Skylab fluids were programmed in FY 1974.
l From the ASTP request.
m Of the $114 600 000 request for ASTP, $109 600 000 was authorized; the chronological history does not indicate how the $5 000 001) was deducted.
n The FY 1977 budget estimate does not indicate how ASTP funds were programmed in FY 1975; the FY 1976 budget estimate predicts that $32 500 000 would be programmed for Saturn 1B in FY 1975.