Date
.
Jan. 31, 1969
NASA awarded integral launch and
reentry vehicle (ILRV) study contract to Lockheed Missile
& Space Company (clustered or modular reusable flyback
stages), North American Rockwell Corporation (expendable
tank configurations), General Dynamics Corporation
(expendable tank concept and modularized solid propulsion
stages), and McDonnell Douglas Astronautics Company
("triamese" configurations and reusable flyback stages).
Studies were to be concluded in September. In June, however,
these "phase A" studies were extended and redirected at
NASA's request toward a more fully reusable system.
Nov. 1969
NASA received phase A ILRV studies
from its four contractors and an in-house- funded report
from Martin Marietta Corporation.
Dec. 10, 1969
A joint NASA-Department of Defense
Space Shuttle Task Group submitted a "Summary Report of
Recoverable versus Expendable Booster Space Shuttle
Studies," in which the group recommended a fully reusable
system.
Feb. 18, 1970
NASA issued a request for proposals
for phase B definition studies of a fully reusable Shuttle
system (proposals due March 30).
May 9, 1970
NASA awarded a North American
Rockwell-General Dynamics team an 11-month contract (phase
B) to define more fully their Shuttle concept. NASA also
selected McDonnell Douglas-Martin Marietta to produce a
competitive design.
June 15, 1970
NASA chose four firms to conduct
11-month feasibility studies on alternative Shuttle designs:
Grumman Aerospace Corp.-Boeing Company (stage-and-a-half
Shuttle with expendable propulsion tanks, reusable orbiter
with expendable booster, reusable booster with solid
propulsion auxiliary boosters), Lockheed (expendable tank
orbiter), and Chrysler Corp. (single-stage reusable
orbiter).
Aug. 26, 1970
NASA announced that Convair Div.,
General Dynamics, would conduct an eight- month design study
for a high-energy upper stage that could be used as an
expend-able upper stage with Shuttle.
Sept. 28, 1970
NASA's Marshall Space Flight Center
chose McDonnell Douglas to conduct a study of an expendable
second stage for a reusable Shuttle booster.
Nov. 19, 1970
Marshall awarded a one-year
modification to its Shuttle study contract with McDonnell
Douglas; the contractor would also be responsible for
testing the structural components of its proposed Shuttle
booster.
June 10, 1971
Marshall was officially assigned the
role of manager of the Shuttle main engine and
booster.
June 16, 1971
NASA Administrator James C. Fletcher
indicated that the agency may take a "phased approach" to
Shuttle development. Hardware for the orbiter would be
developed first, which could be used with an expendable
booster. Development of a reusable booster would
follow.
July 1, 1971
Phase B definition contracts with
North American Rockwell-General Dynamics and McDonnell
Douglas-Martin Marietta, and study contracts with
Grumman-Boeing and Lockheed were extended through October to
consider the phased approach to Shuttle design and the use
of existing liquid or solid propulsion boosters as interim
Shuttle launch vehicles.
Summer 1971
Martin Marietta engineers concluded
that the Titan launch vehicle could be used as an interim
expendable booster for Shuttle.
Sept . 1971
Grumman-Boeing officials suggested
that Saturn IC could serve as an interim Shuttle booster and
that a winged Saturn reusable booster was feasible.
Oct. 7, 1971
Studies being conducted by North
American Rockwell-General Dynamics, McDonnell Douglas-Martin
Marietta, Grumman-Boeing, and Lockheed were extended again
to examine ballistic recoverable boosters.
Dec. 6, 1971
NASA awarded contracts for
feasibility studies of pressure-fed engines for a water-
recoverable Shuttle booster to TRW, Inc., and
Aerojet-General Corporation.
Jan. 27, 1972
Marshall chose Aerojet-General,
Lockheed Propulsion Company, Thiokol Chemical Company, and
United Technology Center to study the use of 120-inch and
156-inch solid motors as part of the Shuttle booster
package.
March 15, 1972
For economic reasons, NASA
Headquarters officials chose the solid booster
con-figuration for Shuttle over the development of a new
liquid fueled system. Two 156-inch-diameter, 140-foot-tall
solid rocket boosters (SRBs) paired with the orbiter's
liquid fueled main engines would boost the Shuttle to orbit.
At an altitude of 1.24 kilometers, the boosters would be
jettisoned, and their descent to the Atlantic slowed by
parachutes. The two boosters would be recovered from the
ocean and refurbished for another mission. The two solid
boosters would be mounted on either side of a larger
external propulsion tank that would feed the orbiter's main
engines. The orbiter would be mounted to the tank (see fig.
1-5).
June 21, 1972
Six firms submitted proposals to
Marshall for a parachute system for the Shuttle solid
boosters.
Sept. 7-8, 1972
NASA held a review at Marshall to
advise industry on its plans for Shuttle's external
propulsion tank and solid rocket boosters.
Dec. 12-13, 1972
A second review session was held at
Marshall for 350 industry and government representatives
interested in the external tank and SRB. A similar meeting
took place on March 6, 1973.
Feb. 10- March 10, 1973
Water impact and towing tests of a
Shuttle SRB-type motor were conducted by the U.S. Navy at
Long Beach, California, for Marshall.
July 16, 1973
Marshall issued a request for
proposals for Shuttle solid rocket motor development to
Aerojet-General Solid Propulsion Company, Lockheed, Thiokol,
and United Technology Center (proposals due Aug.
27.).
Nov. 1973
Marshall conducted drop tests of a
solid rocket motor scale model and a three- parachute
recovery system.
Nov. 20, 1973
NASA selected Thiokol to design,
develop, and test the Shuttle SRB. This six-year contract
was scheduled to run through September 1979.
Jan. 1974
Lockheed protested to the General
Accounting Office (GAO) NASA's selection of Thiokol as
designer of the SRB. Because of the protest, NASA issued
Thiokol a 90-day study contract on February 13 so the firm
could continue its work while GAO studied the situation. The
study contract was extended again on May 20 for 45
days.
June 1974
United Technology Center submitted an
unsolicited proposal to be a backup contractor to Thiokol in
the solid rocket motor program.
June 26, 1974
A letter contract was awarded to
Thiokol by Marshall for the development of the SRB. GAO had
completed its investigation of the agency's procedures in
evaluating the SRB proposals and on June 24 recommended that
NASA decide whether or not the selection of Thiokol should
be reconsidered.
May 15, 1975
NASA issued Thiokol a contract for
solid rocket motor design, development, testing, and
engineering for the period July 26, 1974 through June 30,
1980.
August 7, 1975
Marshall chose the Chemical Systems
Division, United Technology Corporation, to supply the SRB
separation motors. Each booster would require eight
separation motors.
Aug. 22, 1975
Marshall chose McDonnell Douglas to
procure SRB structures (aft skirts, rings, struts,
frustrums, nose caps).
Nov. 1975
NASA officials decided to use the
vehicle assembly building at launch complex 39 at the
Kennedy Space Center to assemble the SRBs.
Jan. 8, 1976
Marshall issued a request for
proposals for an SRB decelerator (parachute) subsystem. The
36.5-meter-diameter chutes would be tested at Marshall and
at NASA's Dryden Flight Research Center.
May 28, 1976
Martin Marietta was chosen by
Marshall to produce the SRB decelerator subsystem. Pioneer
Parachute Company would serve as a subcontractor to Martin
Marietta.
Sept. -Oct. 1976
Engineers at Marshall tested the
thrust vector control system for the SRB.
Dec. 21, 1976
Marshall selected United Space
Boosters, Incorporated, as the assembly contractor for the
SRB.
June 1977
The SRB recovery system was tested at
the National Parachute Test Range, El Centro, California.
One drogue and three main chutes made up the system.
July 18, 1977
The Shuttle solid rocket motor was
test fired for the first time (DM-I). In two minutes, the
motor produced more than 12 million newtons thrust.
Jan. 19, 1978
The Shuttle booster solid rocket
motor was fired successfully a second time (DM-2).
April 1978
The first full-design-limit tests of
the SRB recovery system were conducted at the National
Parachute Test Range. Further tests were held in
July.
Sept. 12, 1978
The Shuttle SRB parachute drop test
program was completed.
Oct. 19, 1978
The Shuttle solid rocket motor was
successfully fired a third time (DM-3).