-
SP-4012 NASA HISTORICAL DATA BOOK: VOLUME III
- PROGRAMS AND PROJECTS 1969-1978
-
Table 2-47. Chronology of Skylab
Development and Operations
|
Date
|
Event
|
|
.
|
|
Feb. 20, 1959
|
NASA Deputy Administrator Hugh L.
Dryden told the Senate Committee on Aeronautical and Space
Sciences that one of the agency's long-range goals was a
permanent manned orbiting laboratory. During the following
spring, several groups within NASA studied the concept of an
orbiting laboratory as one project that might follow Project
Mercury. (In its 1960 budget, NASA requested $2 million to
study methods of constructing a manned laboratory or
converting the Mercury spacecraft into a two-man
laboratory.)
|
|
June 8, 1959
|
In a report prepared for the Army
Ballistic Missile Agency, Wernher von Braun suggested that a
space station could be designed around a spent booster stage
(a concept that was later called the "wet workshop").
|
|
July 10, 1959
|
A conference at Langley Research
Center (LRC) considered the problems associated with
developing the technology to build, launch, and operate a
manned space station.
|
|
Apr. 20-22, 1960
|
The Institute of the Aeronautical
Sciences, NASA and RAND Corp. sponsored a Manned Space
Stations Symposium.
|
|
Oct. 1961
|
Emanuel Schnitzer of LRC suggested
using Apollo hardware to build a space laboratory. The
"Apollo X" vehicle would consist of a standard command and
service module (CSM) with an added inflatable spheroid
structure and transfer tunnel. This suggestion led others
within NASA to think about adapting Apollo-developed
hardware to laboratories and stations.
|
|
Apr. 1961
|
Manned Spacecraft Center (MSC)
personnel prepared a preliminary document that outlined
areas of investigation for a space station study
program.
|
|
May 10, 1962
|
John C. Fischer, Jr., of Lewis
Research Center suggested a two-phase approach to a space
station program: first, a manned station that would operate
for four to six years, being resupplied and remanned by
ferry craft, followed by an inflatable station with
artificial gravity.
|
|
July 31-Aug. 1, 1962
|
LRC hosted a forum for NASA
researchers interested in space station work.
|
|
Sept. 28, 1962
|
At a meeting at NASA Headquarters,
personnel from the Office of Manned Space Flight (OMSF), the
Office of Advanced Research and Technology (OART), MSC,
Marshall Space Flight Center (MSFC), and LRC agreed that the
concept of a space station was an important one for the
future and that advanced technological work should proceed
at the centers.
|
|
Mar. 1, 1963
|
MSC proposed constructing an 18-man
station from hardware under development for Apollo.
|
|
Mar. 28, 1963
|
Abraham Hyatt of NASA Headquarters
organized a task team to study the concept of a manned
earth-orbiting laboratory.
|
|
Apr. 11, 1963
|
The leaders of MSC's Flight
Operations Division met with LRC personnel to discuss the
Virginia center's proposed four-man Manned Orbital Research
Laboratory. On June 24, LRC announced that The Boeing Co.
and Douglas Aircraft Co., Inc., had been selected to study
the concept.
|
|
Aug. 17-Sept. 14,1963
|
NASA and the Department of Defense
(DoD) signed a joint agreement to coordinate their studies
of advanced space exploration, including any manned space
station concepts.
|
|
Dec. 10, 1963
|
DoD announced that funds that had
been set aside for the X-20 Dyna Soar project, which had
been cancelled, would be rechanneled to the Air Force's
Manned Orbiting Laboratory (MOL) project. NASA would provide
technical support to this exclusively military
project.
|
|
March 1964
|
The Lockheed-California Co. delivered
the results of its study of a rotating manned orbital
research laboratory. The laboratory, which would be launched
by a Saturn V, would accommodate a crew of 24 and be
operational for I to 5 years.
|
|
Aug. 17, 1964
|
In a revival of the "Apollo X"
concept, MSC's Spacecraft Integration Branch offered its
proposal for an orbiting laboratory. The 2-man laboratory
would be launched by a Saturn IB for a 14- to 45-day
mission. Other configurations included a 3-man, 45-day
mission; a 3-man, 45-day mission in a double-laboratory
module; and a 3-man, 120-day mission in an independent
systems module.
|
|
Dec. 11, 1964
|
LRC awarded Boeing a 10-month
contract to study the feasibility of designing and launching
a manned orbital telescope.
|
|
June 18, 1965
|
LRC awarded Douglas a follow-on study
contract for the Manned Orbital Research Laboratory, which
would emphasize the Apollo Extension System effort (use of
Apollo-era technology).
|
|
July 30, 1965
|
Lockheed-California delivered its
report to MSC on a modular multipurpose space station.
Configurations included: 45-day, 3-man, 1-compartment lab;
1-year, 6-man, 2-compartment lab; 90-day, 3- to 6-man,
2-compartment lab; 1- to 5-year, 6-to 9-man, 6-compartment
station; and 5- to 10-year, 24- to 36-man, Y-configuration
station.
|
|
Aug. 6-10, 1965
|
NASA Headquarters established the
Saturn/Apollo Applications Office within OMSF. The new
office would be responsible for the Apollo Extension System
effort, among other projects. David M. Jones was acting
director, John H. Disher deputy director.
|
|
Aug. 20, 1965
|
Designers at MSFC began seriously to
investigate the concept of a Saturn IVB-stage orbital
workshop - the in-orbit conversion of a spent S-IVB stage to
an orbital laboratory by an Apollo crew launched separately.
MSFC asked for the assistance of MSC and Douglas, the
manufacturer of the stage, in this four-month design
study.
|
|
Aug. 25, 1965
|
President Lyndon B. Johnson approved
DoD's development of the MOL.
|
|
Sept. 10, 1965
|
The Apollo Extension System effort
was renamed the Apollo Applications Pro-gram. NASA
Headquarters assigned MSC responsibility for spacecraft
development, crew activities, mission control and flight
operations, and payload integration; MSFC responsibility for
launch vehicle development; and the Kennedy Space Center
(KSC) responsibility for prelaunch and launch activities.
William B. Taylor, director of the Apollo Applications
Program, named Joseph G. Lundholm manager of Apollo
applications experiments.
|
|
Oct. 20, 1965
|
Officials from MSC and MSFC held
their first orbital workshop coordination meeting. In
December, the orbital workshop (OWS) became a separate
project at MSFC, with the support of OMSF.
|
|
Nov.1965
|
North American Aviation, Inc.,
delivered to MSC its technical proposal for the Apollo
applications-era CSM.
|
|
Jan. 1966
|
Douglas submitted its summary report
on the Manned Orbital Research Laboratory to LRC. The study
demonstrated the feasibility of launching, operating, and
maintaining an orbital laboratory and examined how such a
laboratory could be used.
|
|
Feb. 11, 1966
|
MSFC submitted to NASA Headquarters a
project management proposal for an Apollo telescope mount
(ATM) to be used with an Apollo-derived orbital laboratory
or an Apollo spacecraft (lunar module). The ATM was based on
an engineering and definition study completed by Ball
Brothers Research Corp. (Sept. 1965-Apr. 1966).
|
|
Mar. 21, 1966
|
The Military Operations Subcommittee
of the House Committee on Government Operations recommended
combining NASA's Apollo Applications Program with the Air
Force's MOL. NASA and DoD created a Manned Space Flight
Experiments Board to coordinate their experiment
programs.
|
|
Mar. 23, 1966
|
In their first schedule, personnel in
the Apollo Applications Program planned 26 Saturn IB and 19
Saturn V launches, including 3 S-IVB wet workshops, 3 S-V
orbital laboratories, and 4 ATMs.
|
|
Apr. 18, 1966
|
MSC granted study contracts to
Douglas, Grumman Aircraft Engineering Corp., and McDonnell
Douglas Corp. for definition studies on the OWS experiment
sup-port module (by Aug. called the airlock module).
|
|
May 20-21, 1966
|
Representatives from NASA and the Air
Force met to discuss proposed medical experiments for the
Apollo Applications Program and MOL.
|
|
June 1, 1966
|
NASA Headquarters selected Martin
Marietta Corp. and Lockheed to perform final definition
studies for the payload integration aspect of Apollo
application missions.
|
|
July 6, 1966
|
George M. Low became acting manager
of MSC's new Apollo Applications Pro-gram Office, Robert F.
Thompson the assistant manager; Leland F. Belew became
MSFC's Apollo applications manager. An Experiments Office
was also established at MSFC.
|
|
July 13, 1966
|
A Saturn/Apollo Applications Mission
Planning Task Force led by William D. Green, Jr., was
created to oversee and coordinate the mission definition
process for proposed Apollo applications missions.
|
|
July 13, 1966
|
Program management for the ATM was
assigned to MSFC.
|
|
July 14, 1966
|
NASA and DoD established a Joint
Manned Space Flight Policy Committee to coordinate their
manned spaceflight activities.
|
|
July 18, 1966
|
David Jones assumed management
responsibility at NASA Headquarters for the development of
the OWS and the experiment support module.
|
|
July 26, 1966
|
It was formally announced at NASA
Headquarters that OMSF had full responsibility for Apollo
and Apollo applications missions; the Office of Space
Science and Applications would select experiments to be
flown aboard these missions and analyze the results; OART
would be responsible for choosing technical experiments; the
Office of Tracking and Data Acquisition would satisfy the
communications re- quirements for the experiments.
|
|
Aug. 19, 1966
|
NASA selected McDonnell Douglas to
manufacture an airlock module (formerly called the spent
stage experiment support module) for the Apollo Applications
Program by which astronauts would enter the empty hydrogen
tank of a spent S-IVB stage (OWS). A contract was approved
on Dec. 6
|
|
Oct. 25, 1966
|
MSFC distributed its research and
development plan for the OWS.
|
|
Nov. 8, 1966
|
NASA Headquarters announced plans for
the first 4 Apollo applications missions: SAA-209 - 28-day
manned test flight of the block 11 CSM; SAA-210 - launch of
an unmanned OWS with airlock module and multiple docking
adapter; SAA-211 - 56- day visit to the OWS by an Apollo
crew; and SAA-212 - unmanned lunar module- ATM
flight.
|
|
Nov. 30, 1966
|
Charles W. Mathews became director of
Saturn/Apollo applications at NASA Headquarters.
|
|
Apr. 18- 19, 1967
|
Personnel from MSC and MSFC met to
review the S-IVB stage for acceptability as a habitable
vehicle. This was followed in May by a preliminary design
review to evaluate the basic design approach the team was
taking toward the spent-stage OWS.
|
|
July 26, 1967
|
NASA selected Martin Marietta to
perform payload (experiments and experiments support
equipment) integration tasks. This contract was definitized
on Jan. 30, 1969. On the same day, the agency awarded Boeing
a contract for long-lead-time materials for two additional
Saturn Vs.
|
|
Oct. 3, 1967
|
In a revised schedule (see Mar. 23,
1966) that reflected budget cutbacks, NASA Headquarters
announced that it was planning 4 Apollo applications
lunar-activity missions, 17 Saturn IB launches, 7 Saturn V
launches, 2 OWSs, I Saturn V workshop, and 3 ATMs.
|
|
Nov. 18-19, 1967
|
At meetings held at NASA Headquarters
and at MSFC, representatives from MSC proposed a dry
workshop (also called the Saturn V workshop) as a better
choice for an Apollo applications laboratory; the adoption
of the dry workshop concept would solve the habitability
problems they had been having with the spent-stage
concept.
|
|
Dec. 4, 1967
|
Thompson became manager of MSC's
Apollo Applications Program Office.
|
|
Jan. 9, 1968
|
Additional budget cuts required
another change to the Apollo applications mission schedule
(see Oct. 3, 1967): 3 Saturn IB launches, 3 Saturn V
launches, I OWS, I Saturn V workshop, I ATM to be flown with
a workshop and 2 lunar missions. The first OWS launch was
scheduled for Apr. 1970.
|
|
Jan. 9, 1968
|
MSFC awarded Parker-Elmer Corp. a
contract to develop the telescopes for the ATM.
|
|
Jan. 16-17, 1968
|
A preliminary design review of the
multiple docking adapter for the OWS was held at
MSFC.
|
|
Jan. 23, 1968
|
The airlock module was given the
additional task of housing the electrical power
conditioning, storage, and distribution system.
|
|
Apr. 3-15, 1968
|
In response to increased budget cuts,
NASA managers concluded that the most practical near-term
Apollo applications mission was a simplified Saturn
IB-launched workshop.
|
|
June 4, 1968
|
In another schedule revision (see
fan. 9, 1968), NASA announced that Apollo applications
missions planning now called for 11 Saturn IB launches, I
Saturn V launch, 1 OWS, I backup OWS, I Saturn V workshop
and I ATM. The first OWS launch was scheduled for Nov.
1970.
|
|
Sept. 23-26, 1968
|
A preliminary design review of the
ATM was held at MSFC.
|
|
Dec. 1, 1968
|
Technical management of the airlock
module was transferred from MSC to MSFC.
|
|
Dec. 18, 1968
|
William C. Schneider became director
of the Apollo Applications Program.
|
|
Jan. 8, 1969
|
An Apollo Applications Program
baseline configuration review was held at NASA Headquarters;
a second review took place on May 22.
|
|
Feb. 26, 1969
|
NASA announced it would negotiate
with North American Rockwell for modifications to four
Apollo spacecraft for Apollo applications missions.
|
|
May 21, 1969
|
At a meeting at MSC, NASA personnel
from Headquarters and the centers discussed what options the
Apollo Applications Program could recommend. Most of the
discussions concerned using a dry rather than a wet
workshop. On the 23rd, MSFC Director von Braun voted for a
Saturn V-launched dry workshop. On the 26th, MSC Director
Robert R. Gilruth also cast his center's lot with the dry
concept.
|
|
May 10-23, 1969
|
DoD cancelled its MOL program. NASA
requested that the MOL food and diet contract with Whirlpool
Corp. and the spacesuit development contract with Hamilton
Standard Div., United Aircraft Corp., be transferred to
it.
|
|
July 18, 1969
|
Based on information presented on
July 8-9, NASA Administrator Thomas O. Paine approved the
shift from a wet to a dry OWS. The latest mission schedule
(see also June 4, 1968) left only four launches, the first
of which would take place in July 1972. The change to the
dry concept was announced to the public on the 22rd.
|
|
Aug. 4, 1969
|
Seven MOL astronaut-trainees were
transferred from the Air Force to NASA.
|
|
Aug. 8, 1969
|
MSFC definitized its contract with
McDonnell Douglas for two OWSs; the second workshop would
serve as a backup.
|
|
Feb. 13, 1970
|
Kenneth S. Kleinknecht became manager
of MSC's Apollo Applications Program.
|
|
Feb. 17, 1970
|
The Apollo Applications Program was
renamed the Skylab Program.
|
|
Mar. 7, 1970
|
In stating his proposed space goals
for the 1970s, President Richard M. Nixon included an
experimental space station as one of his six
objectives.
|
|
May 26, 1970
|
The ATM critical design review was
completed at MSFC; this review gave formal approval to the
ATM design.
|
|
Aug. 10-14, 1970
|
The airlock module critical design
review was held at McDonnell Douglas.
|
|
Aug. 24-27, 1970
|
The multiple docking adapter critical
design review was held at Martin Marietta.
|
|
Aug. 28, 1970
|
MSFC modified its contract with
McDonnell Douglas to reflect the switch from the wet to the
dry workshop.
|
|
Aug. 31, 1970
|
NASA's latest launch schedule (see
July 18, 1969) called for the launch of Skylab I on Nov. 1,
1972.
|
|
Sept. 14-18,1970
|
An OWS critical design review was
conducted at McDonnell Douglas.
|
|
Jan. 19-21, 1971
|
A solar array system critical design
was held at TRW, Inc.
|
|
Apr. 13, 1971
|
The most recent published launch
schedule (see also Aug. 31, 1970) listed Apr. 30, 1973, as
the date of the first Skylab launch.
|
|
May 9, 1971
|
A flight hardware meteoroid shield
development test was performed on the OWS flight article.
Although the shield did not deploy fully and took longer
than expected to deploy, it was concluded that development
would have been successful if performed in orbit.
|
|
Sept. 24, 1971
|
McDonnell Douglas delivered the
Skylab payload shroud, the first major piece of hardware to
be completed, to KSC.
|
|
Nov. 15, 1971
|
NASA Headquarters formed a Manned
Space Flight Team to conduct a mid-term review of Skylab;
the team's report, delivered in Jan. 1972, expressed
confidence that the Apr. 30, 1973, launch date could be
met.
|
|
Jan. 1972
|
The prime crews for the Skylab
missions were announced: Skylab 2 - Charles Conrad, Jr.,
Joseph P. Kerwin, and Paul J. Weitz; Skylab 3 - Alan L.
Bean, Owen K. Garriott, and Jack R. Lousma; and Skylab 4 -
Gerald P. Carr, Edward G. Gibson, and William R. Pogue (the
launch of the workshop would be termed Skylab 1).
|
|
Apr. 6, 1972
|
NASA and the National Science
Teachers Association announced the 25 finalists in the
Skylab Student project who had proposed feasible flight
experiments for Skylab.
|
|
June 7-8, 1972
|
A launch vehicle design certification
review was held at MSCF; launch vehicles for Skylab I and 2
were found acceptable.
|
|
June 21, 1972
|
A CSM design certification review was
held at MSC; the CSM was found accept-able.
|
|
July 18-19, 1972
|
The first CSM for Skylab was
delivered to KSC.
|
|
Sept. 15, 1972
|
A mission operations design
certification review was held at MSC; preparations for all
mission operations requirements were found to be
satisfactory.
|
|
Sept. 22, 1972
|
The ATM arrived at KSC.
|
|
Sept. 23, 1972
|
The Skylab 1 OWS was moved inside the
vehicle assembly building at KSC.
|
|
Oct. 2-3, 1972
|
A modules and experiments design
certification review was held at MSFC.
|
|
Oct. 3-29, 1972
|
During tests of the meteoroid shield
at KSC, problems were encountered with it deploying
properly. It was successfully deployed on the 22d and judged
acceptable for flight.
|
|
Jan. 29-30, 1973
|
Checkout of the airlock module,
multiple docking adapter, and ATM flight units was completed
at KSC, and the units were mated to the OWS and the OWS to
its Saturn V launch vehicle.
|
|
Feb. 19, 1973
|
Robert A. R. Parker was named Skylab
program scientist.
|
|
Feb. 27, 1973
|
Mated Apollo spacecraft and Saturn IB
launch vehicle (Skylab 2) were transferred from the vehicle
assembly building to Launch Complex 39B.
|
|
Apr. 5, 1973
|
The flight readiness test for Skylab
2 was completed.
|
|
May 14, 1973
|
During the launch of the Skylab OWS
(Skylab 1), the meteoroid shield failed to deploy properly;
as a result one of the solar panels was torn off and the
second one became jammed. The laboratory was placed in the
desired near-circular orbit, but its internal temperature
increased beyond acceptable limits for habitability. The
launch of Skylab 2, scheduled for the 15th, was
postponed.
|
|
May 22, 1973
|
A board of investigation was
established to assess the anomalies that occurred dur-ing
the launch of Skylab 1.
|
|
May 23-24, 1973
|
A design certification review was
held for the revised Skylab 2 mission, during which the crew
would erect a "parasol" of ultraviolet-resistant material
(aluminized Mylar/nylon laminate) to protect the workshop
from the heat of the sun. The parasol was conceived,
developed, and constructed in seven days at the Johnson
Space Center (JSC, formerly MSC).
|
|
May 25, 1973
|
Skylab 2 was launched successfully at
9:00 a.m. (all times EDT). Six hours later the Apollo
spacecraft was in position to rendezvous with Skylab; the
crew soft- docked at 5:56 p.m.
|
|
May 26, 1973
|
The Skylab 2 crew entered the OWS,
finding a hot but habitable environment that allowed them to
work for 10- to 15-minute intervals. The parasol was
deployed in 2 1/2 hours, leading to an immediate temperature
decrease in the workshop.
|
|
June 7, 1973
|
The Skylab 2 crew freed the
undeployed solar array.
|
|
June 11, 1973
|
The mated Skylab 3 spacecraft and
launch vehicle were moved to Launch Complex 39B.
|
|
June 22, 1973
|
Skylab 2 splashed down in the Pacific
Ocean at 9:49 a.m. after a mission lasting more than 28
days. The crew was found to be in good health.
|
|
June 29, 1973
|
The Skylab 3 flight readiness test
was completed.
|
|
July 28, 1973
|
Skylab 3 was launched successfully at
7:11 a.m. The crew docked with the laboratory 8 1/2 hours
later.
|
|
Aug. 6, 1973
|
A more refined thermal parasol
developed at MSFC was erected over the original one,
lowering the cabin temperature even more.
|
|
Aug. 13, 1973
|
NASA Headquarters officials moved to
delete the backup Skylab workshop from the program
schedule.
|
|
Aug. 14, 1973
|
The mated Skylab 4 spacecraft and
launch vehicle were moved to Launch Complex 39B.
|
|
Sept. 5, 1973
|
The Skylab 4 flight readiness test
was completed.
|
|
Sept. 25, 1973
|
Skylab 3 splashed down in the Pacific
Ocean at 6:20 p.m. after a mission lasting more than 59
days. The crew exhibited no adverse reactions to the lengthy
visit
|
|
Nov. 6, 1973
|
Because hairline cracks were
discovered in the fins of the S-IB launch vehicle, the
launch was postponed from 10 to 16 Nov. while the fins were
replaced.
|
|
Nov. 16, 1973
|
Skylab 4 was launched successfully at
10:01 a.m. Docking with the workshop took place 8 hours
later.
|
|
Dec. 25-29, 1973
|
The Skylab 4 crew photographed the
Comet Kohoutek prior to and after perihelion. This
photography assignment was added to the original experiments
agenda when the comet was discovered in March 1973.
|
|
Feb. 8, 1974
|
Skylab 4 splashed down in the Pacific
Ocean at 11:17 a.m. after a mission lasting more than 84
days. The crew returned in good health. This mission
concluded the program.
|
|
Mar. 5, 1974
|
Skylab program offices were closed
down at NASA Headquarters and at the field centers.
|
|
1978
|
Although program officials had
predicted that Skylab's orbit would not start to decay until
1983 when Shuttle would be available to assist it during
reentry, data examined by NASA and the North American Air
Defense Command (NORAD) indicated that decay and reentry
would take place much sooner. Active ground control of
Skylab in a low-drag attitude was initiated to extend the
decay date.
|
|
Jan. 1979
|
NASA officials decided to attempt a
form of drag modulation (the drag of the vehicle and its
flight duration would be altered by ground control) to
control Skylab's orbital decay and reentry position.
|
|
June 1979
|
The vehicle, becoming difficult to
control, was placed in a more suitable attitude.
Preparations for Skylab's reentry were coordinated among
NASA, the Department of State, the Federal Preparedness
Agency, DoD, and the Federal Aviation Ad-ministration.
Studies were made of population distribution between
50° north and 50° south latitude and the predicted
reentry footprints. It was determined that the ground
controllers would lose their command of the spacecraft at an
altitude of 130-139 kilometers, after which it would tumble
and change its drag; to combat this the controllers would
intentionally tumble Skylab at 139 kilometers. By so doing,
the pieces of the vehicle left after reentry would have a
better chance of landing in the ocean and not impacting a
continent. In late June, NORAD predicted the reentry date as
July 11. Impact could possibly take place near such major
cities as Caracas, Lagos, Montreal, Rio de Janeiro, Tokyo,
or Washington. But the trend in predictions was generally
that the last revolution would be over the lowest population
area of all.
|
|
July 11, 1979
|
Because predictions made at NORAD and
MSFC at 12 hours before reentry put the impact point just
off the east coast of North America, NASA delayed the
reentry by 30 minutes by tumbling the spacecraft at 148
kilometers, which moved the target area to a long stretch
over the Atlantic and Indian Oceans. Skylab overshot the
target area, with pieces of debris falling into the Indian
Ocean and Western Australia. The reentry footprint was a
narrow band (approximately 4° wide), beginning at about
48° south, 87° east and ending at about 12°
south, 144° east. No in-juries or property damage was
reported.
|
- Back -