1962-1963
NASA sponsored three studies of
reusable spacecraft: North American Aviation (NAA) and
Boeing studied the feasibility of reusable launcher vehicles
capable of carrying 90 000 kg to earth orbit; Lockheed
Missiles & Space studied recoverable 10-passenger
orbital transporters.
1965
Lockheed and General Dynamics (GD)
submitted a joint study to NASA of reusable orbital
shuttles.
1966
Martin Marietta concluded a study for
NASA on a reusable spacecraft design.
1966-1968
NASA conducted its own study of a
fully reusable two-stage transporter.
Feb. 1968
NASA officials told members of
Congress of their interest in a reusable spacecraft- launch
vehicle system.
Jan. 1969
NASA awarded four nine-month
contracts (phase A) for studies of an Integral Launch and
Reentry Vehicle (ILRV): Lockheed, General Dynamics (GD),
McDonnell Douglas, and North American Rockwell (NR). Reports
were received in November.
Feb.1969
The Manned Spacecraft Center (MSC)
began an in-house study of a straight-wing, two-stage, fully
reusable shuttle.
Apr. 1969
NASA and the Department of Defense
(DoD) began a three-month joint study of how an earth
orbital shuttle would serve the needs of both agencies. In
June, the two organizations endorsed the idea of sharing the
same design. In February 1970, a joint NASA-USAF committee
was established.
Apr. 5, 1969
NASA Hq. established a Space Shuttle
Task Group in the Office of Manned Space Flight
(OMSF).
Sept. 1, 1969
President Nixon's Space Task Group,
which was established to advise the President on space
program goals for the next decade, recommended funding for a
reusable shuttle craft to be operational by 1975-1977.
Funding for a space station, the other half of an ambitious
Space Transportation System that NASA wanted to implement
during the next 10 years, was not approved.
Feb. 18, 1970
NASA issued a request for proposals
(RFP) for phase B Shuttle definition studies, due in March.
NR teamed with American Airlines and McDonnell Douglas with
TRW to conduct their 11-month studies under phase B
funding.
March 1970
NASA Hq. established a Shuttle
Program Office within OMSF.
June 1970
NASA announced that it would also be
funding 11-month studies on alternate Shuttle designs.
Contractors chosen were Grumman with Boeing; Lockheed; and
Chrysler. TRW received a contract for an auxiliary
propulsion system definition study.
July 1970
The Langley Research Center (LRC)
awarded a contract to McDonnell Douglas for the study of the
cost of a Shuttle reentry thermal protection system, and the
Mar-shall Space Flight Center (MSFC) and MSC chose the same
contractor to study high and low pressure auxiliary
propulsion systems.
Dec. 11, 1970
NASA held a mid-term review to assess
the studies being conducted by NR and McDonnell
Douglas.
Jan. 5, 1971
President Nixon officially endorsed
the development of Shuttle.
Jan. 19-20, 1971
Of the designs under study, NASA
officials determined the desirability of a delta- wing
designed to accommodate 29 000 kg.
Feb. 1971
Boeing proposed an externally mounted
H2 tank for the Shuttle orbiter. This feature
was incorporated into the phase B and phase A alternate
studies under way.
March 1, 1971
NASA's Mississippi Test Facility was
named as the test site for testing the Shuttle main engines;
Saturn facilities would be modified for the Shuttle tests.
NASA issued RFP's to Aerojet Liquid Rocket Company, Pratt
& Whitney, and Rocketdyne for Shuttle main engine
development.
May 17, 1971
MSC issued an RFP for a Shuttle
thermal protection system.
June 10, 1971
It was announced that MSC had overall
responsibility for the Shuttle program; MSFC was assigned
the booster stages and the main engine; KSC was responsible
for designing the launch and recovery facilities.
June 16, 1971
Primarily for budget reasons, NASA
announced that it would adopt a phased approach to Shuttle
development. A fly-back booster for the orbiter would be
postponed in favor of an interim conventional booster
system. The phase B and alternate studies were extended to
take this phased approach into consideration.
July 12, 1971
MSFC announced that Rocketdyne had
been selected as designer and fabricator of 35 Shuttle main
engines.
July 14, 1971
McDonnell Douglas, General Electric,
and Lockheed received contracts for the development and
testing of a ceramic insulator for Shuttle thermal
protection. NR was awarded a feasibility study contract to
examine a low-cost, reusable chemical stage for the Shuttle
booster.
Aug. 1971
NASA adopted the external tank
configuration for the orbiter, with reentry protection to be
provided by an ablative thermal protection system.
Aug. 3, 1971
Pratt & Whitney requested an
investigation by the General Accounting Office (GAO) of
NASA's selection of Rocketdyne as builder of the Shuttle
main engine. NASA's definitive contract to Rocketdyne was
held pending the investigation; an interim 4-month contract
was signed in September, with extensions granted in February
and March 1972.
Sept. 1971
Phase B contractors presented their
mid-term study results: Boeing&emdash;reusable Saturn V
first stage with added tail, wings, and crew compartment
with attached Grumman orbiter (44 m long, 27-m wingspan)
with external tank; Boeing&emdash;Saturn IC stage expendable
booster that supported orbiter with external tank, plus a
solid propellant booster.
Oct.7, 1971
Phase B contractors were given
another extension to study the feasibility of using
ballistic recoverable boosters.
Jan. 28, 1972
MSC issued an RFP for the development
of low-density ablative materials.
Feb. 1, 1972
MSC called for a design study of an
orbital maneuvering system.
Feb. 22, 1972
NASA began evaluations of phase B
configurations that reflected the addition of solid
propellant boosters.
Mar. 7, 1972
MSC issued an RFP for the study and
development of containerized payload systems.
Mar. 17, 1972
NASA issued an RFP for the
development of a Shuttle, with design due in May.
Mar. 31, 1972
The GAO determined that NASA had
fairly chosen Rocketdyne as contractor for the Shuttle main
engine and gave NASA permission to proceed with the
contract. The definitive contract was processed on August
16, 1972.
Apr. 14, 1972
It was announced that the Kennedy
Space Center (KSC) and Vandenberg Air Force Base, CA, would
be the two Shuttle launching sites.
May 12, 1972
Four companies answered the RFP for a
Shuttle design: NR, McDonnell Douglas, Grumman, and
Lockheed.
May 24, 1972
MSC issued an RFP for the development
of a thermal protection system capable of withstanding
temperatures of 1922 kelvins.
Jul. 20, 1972
McDonnell Douglas was awarded a
12-month contract for a definition study of the orbital
maneuvering system.
Jul. 25, 1972
NASA selected NR as the prime
contractor for the Shuttle (other contenders, in the order
of how their proposals were judged were Grumman, McDonnell
Douglas, and Lockheed). NR subcontracted with Grumman and
McDonnell Douglas for engineering support services. NASA's
definitive contract with NR was signed on April 16, 1973,
superceding a letter contract that was issued on August 9,
1972.
Aug. 9, 1972
NASA was given the authorization to
proceed with a space Shuttle orbiter contract.
Oct. 1972
NR announced that their baseline
design was an orbiter 38.3 m long with a wing span of 25.5
m, weighing 108 000 kg at launch. Two solid boosters would
assist the Shuttle main engine; the propellant tank would be
mounted externally.
Nov. 13, 1972
In a program requirements review,
NASA Hq., MSC, and NR personnel made some changes to the
baseline configuration, increasing the total weight and
thrust by a small amount.
Mar. 29, 1973
Rockwell International (formerly NR),
let four major subcontracts: vertical tail unit to Fairchild
Republic Division of Fairchild Industries, Inc.; double
delta wings to Grumman; mid-fuselage to Convair Aerospace
Division of GD; orbital maneuvering system to McDonnell
Douglas.
Apr. 2, 1973
NASA issued an RFP to McDonnell
Douglas, Boeing, and Martin Marietta for the external tank.
Chrysler also replied to the RFP.
June 26, 1973
Pratt & Whitney TF33-P-7 engines
were chosen for use on Shuttle during its approach and
landing tests.
Aug. 16, 1973
NASA chose Martin Marietta as the
manufacturer of the external tank for the or-biter.
May 17, 1974
The Johnson Space Center (JSC,
formerly MSC) awarded IBM a contract to provide ground-based
computing and data processing system software design for
Shuttle support.
Oct. 18, 1974
NASA announced that the Flight
Research Center at Edwards AFB, California, would be used as
the landing area for the first several Shuttle missions
before at-tempting to use facilities at KSC.
Jan 1975
Program officials announced that a
modified Boeing 747 would be used in drop flight tests of
the orbiter.
Feb. 1975
A Shuttle Preliminary Design Review
was held.
Mar. 13, 1975
Rocketdyne completed the first
Shuttle main engine.
Apr. 9, 1975
JSC awarded a contract to Martin
Marietta for the development of a manned maneuvering unit
for Shuttle EVA.
May 6, 1975
NASA announced that Canada would
finance the development and manufacture of a remote
manipulator system for Shuttle.
June 11, 1975
First in a series of Shuttle main
engine tests was conducted successfully.
Aug. 1975
At Rockwell's Downey, California,
factory, the final assembly and mating of Or-biter 101 was
begun.
Sept. 24, 1975
JSC announced that a new Shuttle
Payload Integration and Development Program Office would
manage all orbiter payloads.
Sept. 29, 1975
A supplementary agreement between
NASA and Rockwell called for an additional $1.8 million for
the completion of orbiters 101 and 102, bringing the total
Rockwell contract value to $2700 million.
Dec. 16, 1975
NASA announced that the Shuttle
Approach and Landing Tests would begin in April 1977 at the
Flight Research Center, Edwards AFB.
Dec. 20, 1975
The shuttle main engine completed its
first 60-second duration test.
Mar. 12, 1976
Orbiter 101 assembly was
completed.
Sept. 17, 1976
Orbiter 101, named Enterprise, was
rolled out of the Rockwell factory doors for
inspection.
Nov. 4, 1976
Modifications were completed to the
Boeing 747 that would be used in the Approach and Landing
Tests.
Jan. 14, 1977
The modified Boeing 747 was delivered
to the Dryden Flight Research Center (DFRC), Edwards
AFB.
Jan. 31, 1977
Orbiter 101 was transported to
DFRC.
Feb. 8, 1977
Orbiter 101 and its carrier aircraft
were mated.
Feb. 18, 1977
The first inert captive flight (2
hr., 5 min.) of Shuttle orbiter 101 was conducted.
Feb. 22, 1977
Second inert captive flight (3 hr.,
13 min.).
Feb. 25, 1977
Third inert captive flight (2 hr., 28
min.).
Feb. 28, 1977
Fourth inert captive flight (2 hr.,
11 min.).
Mar. 2, 1977
Fifth inert captive flight (1 hr., 39
min.).
June 18, 1977
First manned captive active flight
(55 min.).
June 23, 1977
The first main engine was delivered
to the testing site in Mississippi.
June 28, 1977
Second manned captive active flight
(1 hr., 2 min.).
July 8, 1977
The second main engine was delivered
to the testing site.
July 26, 1977
Third manned captive active flight
(59 min.).
Aug. 12, 1977
First free flight approach and
landing (5 min.).
Sept. 13, 1977
Second free flight approach and
landing (5 min.).
Sept. 23, 1977
Third free flight approach and
landing (5 min.).
Oct. 12, 1977
Fourth free flight approach and
landing (2 min.).
Oct. 26, 1977
Fifth and last free flight approach
and landing (2 min.).
Jan. 1978
NASA completed its flight test
program with Orbiter 101.
Mar. 3, 1978
Rockwell completed the assembly of
Orbiter 102.
Mar. 31, 1978
Orbiter 102's external tank was
delivered to MSFC for vertical ground vibration
tests.
Mar. -Dec. 1978
Vertical ground vibration tests were
conducted on Orbiter 101.
July 1978
Orbiter 102, named Columbia, was
rolled out of Rockwell's factory for inspection.
Aug. 1978
Columbia was delivered to KSC.
*For additional information, see table 1-39, and the series of annual chronologies published by NASA: Astronautics and Aeronautics: Chronology of Science, Technology, and Policy for the years 1969-1978 (Washington, 1970-1984).