SP-4012 NASA HISTORICAL DATA BOOK: VOLUME III
PROGRAMS AND PROJECTS 1969-1978

 

Table 3-112. Chronology of Mariner Mars 69 Development and Operations

 

Date

Event

.

Dec. 22, 1965

NASA Headquarters authorized a 1969 Martian flyby project for two Mariner spacecraft to be managed by the Jet Propulsion Laboratory (JPL).

Feb. 11, 1966

The Mariner Mars 69 spacecraft system design team held its first meeting.

Feb. 28, 1966

NASA Hq. approved the Mariner Mars 69 project approval document.

Apr. 7, 1966

NASA limited the experiment candidates to Mars-oriented investigations.

May-Nov. 1966

NASA issued Phase I requests for proposals (RFP).

May 26, 1966

NASA selected experiments for the two spacecraft.

July 31, 1966

Program officials completed a first draft of mission requirements.

Sept.1966

Program officials completed a final draft of the project development plan.

Nov. 15, 1966

JPL completed a spacecraft configuration mockup.

Jan. 10, 1967

The mission operations design team held its first meeting.

Jan.-Mar. 1967

JPL conducted a subsystem preliminary design review.

July-Nov. 1967

JPL conducted spacecraft subsystem detail design reviews.

July 15, 1967

Program officials made concessions to meet FY 1968 budget cuts (they delete the approach system guidance subsystem in Sept. for the same reason).

Nov. 1967

The subcontractor delivered the Centaur launch vehicle engines for AC-19.

Nov. 28. 1967

Officials conducted a launch vehicle system design review.

Dec. 8, 1967

The subcontractor delivered the first spacecraft octagon structure to JPL.

Jan. 22, 1968

Program officials declared that the spacecraft preliminary design phase had been completed.

Mar. 1968

The subcontractor delivered the Centaur engines for AC-20.

Apr. 1968

Contractors completed the assembly of AC-19.

May 22, 1968

Team members delivered the first flight spacecraft structure to the spacecraft assembly facility.

June 5, 1968

NASA approved AC-19.

June 15, 1968

Contractors completed the assembly of AC-20.

June 18, 1968

Team members delivered the second flight spacecraft structure to the spacecraft assembly facility.

July 20, 1968

NASA approved AC-20.

Sept.1968

Contractors delivered AC-19 to the Kennedy Space Center.

Sept. 26, 1968

NASA held a project science review.

Nov.-Dec. 1968

Contractors delivered AC-20 to KSC.

Dec. 1968- Jan. 1969

JPL delivered three Mariner 69 spacecraft to KSC.

Jan. 21, 1969

NASA conducted joint flight acceptance tests with AC-19 and Mariner F.

Jan. 24, 1969

NASA conducted joint flight acceptance tests with AC-20 and Mariner G.

Feb. 1969

NASA conducted launch readiness reviews at KSC, NASA Hq., and JPL.

Feb. 1969

While mating AC-19 and Mariner F, technicians accidentally depressurized the Atlas stage; officials reassigned AC-20 to Mariner F.

Feb. 18, 1969

Technicians mated Mariner F and AC-20.

Feb. 20, 1969

Contractors delivered a new Atlas stage for AC-19.

Feb. 22, 1969

NASA verified Mariner F ready for launch.

Feb. 25, 1969

NASA launched Mariner 6 successfully.

Mar. 20, 1969

NASA verified Mariner G ready for launch.

Mar. 27, 1969

NASA launched Mariner 7 successfully.

July 31, 1969

Mariner 6 flew by Mars, the closest distance to the planet being 3200 kilometers.

Aug. 5, 1969

Mariner 7 flew by Mars.


-
Back -