SP-4012 NASA HISTORICAL DATA BOOK: VOLUME III
PROGRAMS AND PROJECTS 1969-1978

 

Table 3-120. Chronology of Viking Development and Operations

 

Date

Event

.

Aug. 29, 1967

NASA Hq. cancelled the proposed Voyager unmanned Mars landing mission because of budget cutbacks by Congress.

Sept. 6, 1967

NASA's Langley Research Center's (LaRC) Planetary Missions Technology Steering Committee held a planning meeting to determine a follow-on proposal to Voyager.

Oct. 9, 1967

Office of Space Science and Applications officials outlined for Administrator James E. Webb five options for planetary exploration in the 1970s.

Nov. 1967

NASA proposed to Congress an alternative to Voyager: two orbiter-small probe missions to Mars in 1973 and a more ambitious soft-lander mission in 1975. NASA Hq. assigned the former, called Titan Mars 1973 Orbiter and Lander, to LaRC.

Jan. 29, 1968

President Lyndon B. Johnson included approval of the 1973 orbiter-lander Mars mission in his budget address to Congress.

Feb. 9, 1968

OSSA directed LaRC and the Jet Propulsion Laboratory (JPL) to conduct baseline mission studies for the 1973 project. JPL would share in the mission by managing the development of the orbiter; LaRC would have overall management authority and responsibility for the lander.

Winter-Fall 1968

General Electric, McDonnell Douglas, and Martin Marietta conducted mission mode studies for NASA.

May 1968

in response to further budget cuts by Congress, NASA pared down its plans for the 1973 Mars missions.

Aug. 1968

JPL established a Titan-Mars orbiter design team.

Sept. 1968

Gerald Soffen became project scientist.

Sept. 28, 1968

NASA issued a request for solicitation for participation in the development of scientific investigations for the lander.

Oct. 28 - Nov. 14, 1968

LaRC, JPL, and NASA Hq. personnel held a series of meetings at LaRC to define alternative Mars missions for 1973. The group chose a soft-lander mission with extended life and a flyby support module and labeled the proposal Viking.

Nov. 1968-

JPL produced a baseline orbiter conceptual design. Feb. 1969

Dec. 4, 1968

NASA Administrator Thomas 0. Paine approved a more ambitious scheme for an orbiter-lander Viking. The 1973 mission would be launched by a Titan IIID-Centaur.

Dec. 6, 1969

LaRC established an interim Viking Project Office, with James S. Martin, Jr., as project manager.

Feb. 8, 1969

Paine signed the project approval document.

Feb. 11, 1969

NASA invited 38 scientists to participate in the planning for lander experiments.

Feb. 25, 1969

NASA announced the members of the eight Viking science teams.

Feb. 28, 1969

NASA issued a request for proposals (RFP) for the Viking lander. Boeing, McDonnell Douglas, and Martin Marietta responded.

Apr. 17, 1969

JPL established a Viking Orbiter Office, to be managed by Henry W. Norris.

May 29, 1969

NASA chose Martin Marietta Corp. as the prime contractor for the lander.

July 15, 1969

NASA Hq. managers issued an invitation to scientists to work on one of the orbiter or lander science teams or propose alternatives of proposals or additional experiments. NASA received 150 proposals by Oct. 20.

Aug. 11, 1969

The Viking team released an updated project definition document.

Dec. 31, 1969

Administrator Paine determined that the 1973 Viking missions would have to be delayed until 1975 to respond to a budget cut by Congress.

Oct. 19-20, 1971

The Viking team held the orbiter preliminary design review.

Jan.-July 1973

JPL held critical design reviews of the orbiter subsystems.

Apr. 3, 1973

The Viking site selection team made the final decision on landing sites for the two landers.

July 9-10, 1973

NASA conducted the orbiter critical design review.

Jan. 1974

JPL began conducting tests with the proof-test orbiter.

Sept. 27, 1974

Because of budget cuts, JPL could not continue its testing of a third orbiter. The team redesignated the proof-test orbiter Viking Orbiter I and put the third craft in storage. NASA also cancelled the third lander.

Jan. 4, 1975

Martin Marietta delivered the first lander to the Kennedy Space Center, and verification test teams began their work.

Jan. 31, 1975

JPL completed orbiter qualification tests.

Feb. 11, 1975

JPL delivered the first orbiter flight hardware to KSC, where verification tests were begun.

Mar. 8, 1975

NASA engineers mated a Viking lander and orbiter for the first time. They enclosed the pair in the Centaur launch shroud on the 27th.

June 1975

Technicians sterilized the two landers.

Aug. 11, 1975

KSC officials were forced to cancel the countdown for the first Viking mission because of a corroded thrust-vector-control valve. After the postponement, technicians discovered that the orbiter's batteries had been discharged and had to be replaced. The entire spacecraft was removed from the stack, and the second spacecraft was prepared for launch.

Aug. 20, 1975

NASA successfully launched Viking 1.

Sept. 9, 1975

Viking 2 joined the first Mars-bound spacecraft after a successful launch.

Dec. 1975 - June 1976

Viking teams simulated lander and orbiter operations in preparation for actual mission events.

June 21, 1976

Viking I was inserted into its precise orbit of Mars. The first pictures returned by the orbiter indicated that the landing sites chosen for the spacecraft would have to be rejected.

June 27, 1976

Viking managers decided to postpone the July 4 landing while they looked for safer sites.

July 20, 1976

Viking I landed safely on Mars.

Aug. 7, 1976

Viking 2 began its Martian orbits, and the site certification team continued its search for a second landing site.

Sept. 3, 1976

Viking 2 touched down on the Martian surface.

Nov. 15, 1976

NASA terminated the Viking primary mission.

Dec. 1976

Spacecraft controllers reactivated the landers and began an extended mission.

Apr. 1, 1978

NASA terminated the Viking extended mission.

July 25, 1978

Orbiter 2 ceased functioning.

Apr. 12, 1980

NASA shut down Lander 2.

Aug. 7, 1980

Controllers silenced Orbiter 1, but Lander I continued to send signals to earth.


-
Back -