Date
.
May 1966
The Goddard Space Flight Center
awarded three contracts for feasibility studies (Phase A)
for an advanced Applications Technology Satellite (ATS F and
G) to Fairchild-Hiller, General Electric (GE) Company, and
Lockheed Missiles and Space.
July 7, 1966
Goddard issued a request for
proposals (RFP) to industry for an ATS antenna design
study.
Aug. 22, 1966
Goddard received antenna design study
proposals. from nine companies.
Dec. 14, 1966
Goddard awarded an antenna design
study contract to Goodyear.
Jan. 1967
The three contractors completed their
feasibility studies for Goddard.
May 14, 1967
Goodyear completed its antenna
study.
June 27, 1967
NASA exercised its option to continue
its contract with Goodyear and requested the company to
proceed with a detailed design and fabrication of a
full-scale test model of its antenna.
Jan. 16, 1968
NASA issued an invitation to
participate in the ATS F and G missions to potential
investigators.
Feb. 8, 1968
Goddard solicited Phase B/C ATS
proposals from industry.
Sept. 1968
Goddard awarded Phase B/C contracts
to GE and Fairchild.
Oct. 1968
NASA chose 18 experimenters for the
ATS F mission.
Apr. 1969
Goodyear delivered its model antenna
to Goddard.
Aug. 12, 1969
NASA launched ATS 5 into transfer
orbit. Excessive motion caused the spacecraft to spin
transversely. After the motor case was ejected, the
spacecraft began spinning about the proper axis, but going
the wrong direction. The gravity gradient experiments could
not be performed; only secondary experiments were
accomplished.
Sept.1969
GE and Fairchild submitted Phase D
proposals to Goddard.
Dec. 1969
At NASA's direction, GE and Fairchild
submitted revised Phase D proposals, taking into account
recent budget adjustments.
Late 1969-
The source evaluation board charged
with selecting an ATS prime contractor met.
Early 1970
Their initial scoring was Fairchild
699, GE 664. Second scoring was Fairchild 683, GE 670. A
final score showed Fairchild 686, GE 687. They judged the
two proposals to be technically equal; the cost differences
were minor.
Feb. 5, 1970
NASA advised GE and Fairchild that
further budget cuts would cause a delay in launching ATS F
by one year; the agency asked the potential contractors to
submit revised proposals based on the new launch
target.
Feb. 16, 1970
Fairchild advised NASA that it would
try to meet the Feb. 27 deadline for the revised proposal,
but that Mar. 6 was the earliest date it could guarantee
submission.
Feb. 18, 1970
GE advised NASA that it needed
additional time to reply to the request for a revised
proposal; it would try to submit by Mar. 4.
Feb. 25, 1970
Fairchild called Goddard, advising
the center of its intention to submit a telegraphic request
for extension to Mar. 2. (Fairchild later claimed that they
were told by NASA that a similar request from GE had not
been approved and their request could not be approved
either.)
Feb. 27, 1970
Fairchild submitted its proposal at 4
p.m.
Mar. 4, 1970
Fairchild submitted an optional
proposal, which was later rejected. Fairchild also learned
that GE had not yet delivered its bid and asked that its
proposal not be submitted to Goddard personnel until receipt
of GE's, but the proposal had already been
circulated.
Mar. 6, 1970
GE submitted its bid, which had been
revised to show a reduction in overhead costs; the new total
was just below that of Fairchild's.
Mar. 10, 1970
NASA conducted a fact-finding session
with Fairchild at Goddard.
Mar. 11-12, 1970
NASA conducted a fact-finding session
with GE at Goddard.
Apr. 3, 1970
The source evaluation board reported
that the two proposers were technically equal, but that GE's
proposal was approximately 2% lower in cost.
Apr. 7, 1970
The board delivered its oral report
to the NASA administrator.
Apr. 8, 1970
NASA announced that the ATS contract
would be awarded to GE. Fairchild claimed that GE could have
used the extra week it took to deliver its proposal
unfairly, since its contract was already circulating at
Goddard during that time.
Apr. 9, 1970
NASA Administrator Thomas 0. Paine
requested that the General Accounting Office (GAO) review
the events leading to the selection of GE as the contractor
for ATS.
July 2, 1970
GAO advised NASA to reconsider the
selection and reopen the bidding.
July 16, 1970
Paine appointed a Selection Panel and
an ATS Procurement Review Committee to review the decision
to award GE the contract over Fairchild.
Aug. 26, 1970
The committee delivered its
report.
Sept. 5, 1970
On the recommendations of the
committee, NASA reversed its decision and awarded the ATS
contract to Fairchild, based on Fairchild's superior
technical abilities.
Nov. 12, 1970
NASA announced the experimenters for
ATS F.
Spring 1972
Because of cost overruns and other
problems with the contractor management, NASA postponed the
ATS F launch from spring 1973 to spring 1974.
Sept.1972
Lewis Research Center announced that
it would be contracting for a study of an advanced ATS (H/I)
satellite to be launched in 1977-1978. Advanced ATS was
proposed as a new start for FY 1973 by Associate
Administrator John Naugle, but it was not approved by
Congress.
Jan. 1973
Congress decreased funding for NASA's
applications program by $35.7 million. As a result, NASA
decided to cancel the ATS G mission.
Sept.1973
At the Johnson Space Center,
technicians completed the ATS F mechanical and structural
qualifications program.
May 30, 1974
NASA launched ATS 6 successfully. It
was used during its first year of operations to transmit
medical and educational programs to remote communities in
Alaska, the Rocky Mountains, and Appalachia.
May-July 1974
Members of Congress who favor
continuing the ATS program with the launching of ATS G
lobbied for support; they were unsuccessful.
Nov. 1974
NASA directed Fairchild to mothball
the ATS G spacecraft.
May-June 1975
NASA controllers moved ATS 6 from its
initial location in the western hemisphere to a location
over eastern Africa where it can support communications
experiments in India.
July 15-24, 1975
ATS 6 made real-time television
possible during the joint U.S.-USSR Apollo-Soyuz Test
Project.
July 1975
NASA invited organizations to propose
experiments for the third year of ATS 6 operations.
Aug.-Dec. 1976
NASA began moving ATS 6 back to the
western hemisphere in August. It was used along the way in
direct broadcasting experiments in many developing
countries.
May 7, 1979
ATS 6's prime east thruster
failed.
June 30, 1979
NASA terminated ATS 6 services to
users.
July 13, 1979
Two more thrusters failed on ATS
6.
Aug. 6, 1979
NASA boosted ATS 6 out of
geostationary orbit.
Nov. 24, 1979
Ground controllers reactivated ATS 6
for use with a NOAA experiment.