SP-4012 NASA HISTORICAL DATA BOOK: VOLUME III
PROGRAMS AND PROJECTS 1969-1978

 

Table 4-82. Chronology of Nimbus Development and Operations

 

Date

Event

.

Early 1968

Congress approved a follow-on Nimbus program (Nimbus E and F).

June 1968

NASA Headquarters approved a replacement for Nimbus B.

Nov. 1968

Congress cut $6.5 million from the Nimbus budget, forcing the agency to modify its plans.

Jan. 15, 1969

GSFC released an RFP for a Nimbus spacecraft.

Jan. 17, 1969

NASA terminated Nimbus 2 operations after it had successfully completed all its objectives.

Jan. 22, 1969

A project approval document for Nimbus E and F was approved at NASA Headquarters. Nimbus E was scheduled for launch in the second quarter of 1972, Nimbus F for the second quarter of 1973.

Mar. 12, 1969

GE submitted its proposal for Nimbus to GSFC.

Apr. 14, 1969

Nimbus 3 was launched successfully. Operations were ceased in March 1972.

July 1, 1969

GE's phase C contract was extended six months; phase D was shortened from 32 to 28 months.

July 25, 1969

A Nimbus E payload was approved; six of the originally proposed eight experiments were retained.

July 29, 1969

Nimbus 3s IRIS failed.

Aug. 1, 1969

GSFC completed its evaluation of GE's proposal.

Nov. 20, 1969

For Nimbus F, 12 experiments were chosen from 33 proposals for a tentative payload; the number was reduced to 11 in August 1970.

Nov. 26, 1969

The Nimbus program manager recommended a Nimbus follow-on program of two flights (Nimbus G and H).

Feb. 1970

GSFC awarded contracts for Nimbus E experiments.

Mar. 31, 1970

GSFC awarded GE a contract for the fabrication of the Nimbus spacecraft; the contract was definitized in June.

Apr. 8, 1970

Nimbus 4 was launched successfully.

Jan. 25, 1971

The number of experiments being considered for Nimbus F was increased to 14; 12 were approved in March.

Feb. 1972

Because of budget tightening efforts, funds were reallocated from Nimbus to ERTS; three Nimbus experiments under consideration were dropped. GSFC awarded contracts for Nimbus F experiments.

July 1972

The tracking and data relay experiment was removed from Nimbus E, but it was kept as part of Nimbus F.

Dec. 10, 1972

Nimbus 5 was launched successfully; operations were terminated in April 1983.

Mar. 29, 1973

NASA Headquarters sent GSFC guidelines for the initiation of Nimbus G. Nimbus G would provide data on pollution, oceanography, and meteorology; launch was scheduled for early 1977.

Aug. 1, 1973

GE presented a low-cost Nimbus G spacecraft development plan to NASA Headquarters.

Dec. 14, 1973

GE Presented a second cost proposal to NASA for Nimbus G not to exceed $15.66 million.

Mar. 20, 1974

NASA Headquarters briefed OMB on Nimbus G.

Apr. 1974

The launch readiness date for Nimbus F was changed to October 1974.

Nov. 7, 1974

GSFC awarded GE a contract for Nimbus G development.

Nov. 27, 1974

The Nimbus F launch date was changed to May-June 1975.

Apr. 6, 1975

GSFC awarded a contract to Beckman Instruments for a Nimbus G instrument to measure and monitor concentrations of ozone (SBUV/TOMS).

May 1975

The launch date for Nimbus G was estimated as late 1978.

June 12, 1975

Nimbus 6 was launched successfully; operations ended in September 1983.

Sept. 17, 1976

NASA Headquarters reviewed the status of Nimbus G.

Oct. 24, 1978

Nimbus 7 was launched successfully; it was still operational in 1983.


-
Back -