- [40] Development
of the on-board software for the Apollo program was an important
exercise both for NASA and for the discipline of software
engineering. NASA acquired considerable experience in managing a
large, real-time software project that would directly influence
the development of the Shuttle on-board software. Software
engineering as a specific branch of computer science emerged as a
result of experiences with large-size military, civilian, and
spaceborne systems. As one of those systems, the Apollo software
effort helped [41] provide examples both of failure and success
that could be incorporated into the methodology of software
engineering.
-
- In the Apollo program, as well as other
space programs with multiple missions, system software and some
subordinate computer programs are only written once, with some
modifications to help integrate new software. However, each
mission generates new operational requirements for software,
necessitating a design that allows for change. Since 1968, when
designers first used the term software engineering, consciousness
of a software life cycle that includes an extended operational
maintenance period has been an integral part of proper software
development.
-
- Even during the early 1960s, the cycle of
requirements definition, design, coding, testing, and maintenance
was followed, if not fully appreciated, by software developers. A
Bellcomm report prepared for the Apollo program and dated November
30, 1964 could serve as an excellent introduction to the concept
today71. The important difference from present practice was
the report's recommendation that modules of code be limited to 200
to 300 lines, about five times larger than current suggestions.
The main point of the report (and the thrust of software
engineering) was that software can be treated the same way as
hardware, and the same engineering principles can apply. However,
NASA was more used to hardware development than to large-scale
software and, thus, initially failed adequately to control the
software development. MIT, which concentrated on the overall
guidance system, similarly treated software as a secondary
occupation72. This was so even though MIT manager A.L. Hopkins
had written early in the program that "upon its execution rests
the efficiency and flexibility of the Apollo Guidance and
Navigation System"73. Combined with NASA's inexperience, MIT's
non-engineering approach to software caused serious development
problems that were overcome only with great effort and expense. In
the end NASA and MIT produced quality software, primarily because
of the small-group nature of development at MIT and the overall
dedication shown by nearly everyone associated with the Apollo
program74.
-
-
- Managing the Apollo Software
Development Cycle
-
-
- One purpose of defining the stages in the
software development cycle and of providing documentation at each
step is to help control the production of software. Programmers
have been known to inadvertently modify a design while trying to
overcome a particular coding difficulty, thus making it impossible
to fulfill the specification. Eliminating communication problems
and preventing variations from the designed solution are among the
goals of software engineering. In [42] the Apollo
program, with an outside organization developing the software,
NASA had to provide for quality control of the product. One method
was a set of standing committees; the other was the acceptance
cycle.
-
- Three boards contributed directly to the
control of the Apollo software and hardware development. The
Apollo Spacecraft Configuration Control Board monitored and
evaluated changes requested in the design and construction of the
spacecraft itself, including the guidance and control system, of
which the computer was a part. The Procedures Change Control
Board, chaired by Chief Astronaut Donald K. Slayton, inspected
items that would affect the design of the user interfaces. Most
important was the Software Configuration Control Board,
established in 1967 in response to continuing problems and chaired
for a long period by Christopher Kraft. It controlled the
modifications made to the on-board software75. All changes in the existing specification had to
be routed through this board for resolution. NASA's Stan Mann
commented that MIT "could not change a single bit without
permission"76.
-
- NASA also developed a specific set of
review points that paralleled the software development cycle. The
Critical Design Review (CDR) resulted in acceptance of
specifications and requirements for a given mission and placed
them under configuration control. It followed the preparation of
the requirements definition, guidance equation development, and
engineering simulations of the equations. Next came a First
Article Configuration Inspection (FACI). Following the coding and
testing of programs and the production of a validation plan, it
marked the completion of the development stage and placed the
software code under configuration control. After testing was
completed, the Customer Acceptance Readiness Review (CARR)
certified that the validation process resulted in correct
software. After the CARR, the code would be released for core rope
manufacture. Finally the Flight Readiness Review (FRR) was the
last step in clearing the software for flight77. The acceptance process was mandatory for each
mission, providing for consistent evaluation of the software and
ensuring reliability. The unique characteristic of ICs of the
Apollo software appeared at each stage of the software life
cycle.
-
-
- Requirements
Definition
-
-
- Defining requirements is the single most
difficult part of the software development cycle. The
specification is the customer's statement of what the software
product is to do. Improperly prepared or poorly defined
requirements mean that the resulting software will likely be
incomplete and unusable. Depending on the type of project, the
customer may have little or a lot to do with the preparation of
the [43] specification. In most cases, a team from the
software developers works with the customer.
-
- MIT worked closely with NASA in preparing
the Guidance and Navigation System Operations Plan (GSOP), which
served as the requirements document for each mission. NASA's
Mission Planning and Analysis Division at the Manned Spacecraft
Center provided detailed guidance requirements right down to the
equation level78. Often these requirements were in the form of flow
charts to show detailed logic79. The division fashioned these requirements into a
controlled document that contained specific mission requirements,
preliminary mission profile, preliminary reference trajectory, and
operational requirements for spacecraft guidance and navigation.
NASA planned to review the GSOP at launch minus 18 months, 16
months, 14 months and then to baseline or "freeze" it at 13.5
months before launch. The actual programs were to be finished at
launch minus 10.5 months and tested until 8 months ahead, when
they were released to the manufacturer, with tapes also kept at
MIT and sent to Houston, North American (CM manufacturer), and
Grumman (LEM manufacturer) for use in simulations. At launch minus
4 months the core ropes were to be completed and used throughout
the mission80.
-
- In software engineering practice today,
the specification document is followed by a design document, from
which the coding is done. Theoretically, the two together would
enable any competent programmer to code the program. The GSOPs
contained characteristics of both a specification and design
document. But, as one of the designers of the Apollo and Shuttle
software has said, "I don't think I could give you the
requirements for Apollo and have you build the flight
software"81. In fact, the plans varied both in what they
included and in the level of detail requirements. This variety
gave MIT considerable latitude when actually developing the flight
software, thus reducing the chance that it would be easily
verified and validated.
-
-
- Coding: Contents of the Apollo
Software
-
-
- By 1963, designers determined that the
Apollo computer software would have a long list of capabilities,
including acting as backup to the Saturn booster, controlling
aborts, targeting, all navigation and flight control tasks,
attitude determination and control, digital autopilot tasks, and
eventually all maneuvers involving velocity
changes82. Programs for these tasks had to fit in the
memories of two small computers, one in the CM and one in the LEM.
Designers developed the programs using a Honeywell 1800 computer
and later an IBM 36O, but never with the actual flight hardware.
The development computers generated binary object code and a
listing83. The tape [44] containing
the object code would be tested and eventually released for core
rope manufacture. The listing served as documentation of the
code84.
-
-
- Operating System
Architecture
-
-
- The AGC was a priority-interrupt system
capable of handling several jobs at one time. This type of system
is quite different from a "round-robin executive." In the latter
programs have a fixed amount of time in which to run before being
suspended while the computer moves on to the remaining pending
jobs, thus giving each job the same amount of attention. A
priority-interrupt system is always executing the one job with the
highest priority; it then moves on to others of equal or lower
priority in its queue.
-
- The Apollo control programs included two
related to job scheduling: the Executive and the Waitlist. The
Executive could handle up to seven jobs at once while the Waitlist
had a limit of nine short tasks85. Waitlist tasks had execution times of 4
milliseconds or less. If a task ran longer than that, it would be
promoted by the Waitlist to "job" status and moved to the
Executive's queue86. The Executive checked every 20 milliseconds for
jobs or tasks with higher priorities than the current
ones87. It also managed the DSKY
displays88. If the Executive checked the priority list and
found no other jobs waiting, it executed a program called DUMMY
JOB continuously until another job came into the
queue89.
-
- The Executive had other duties as part of
controlling jobs. One solution to the tight memory in the AGC was
the concept of time-sharing the erasable
memory90. No job had permanent claim to any registers in the
erasable store. When a job was being executed, the Executive would
assign it a "coreset" of 12 erasable memory locations. Also, when
interpretive jobs were being ran (the Interpreter is explained
below), an additional 43 cells were allocated for vector
accumulation (VAC). The final lunar landing programs had eight
coresets in the LEM computer and just seven in the CM. Both had
five VACs91. Moreover, memory locations were given multiple
assignments where it was assured that the owning processes would
never execute at the same time. This approach caused innumerable
problems in testing as software evolved and memory conflicts were
created due to the changes.
-
-
- Programming the AGC
-
-
- [45] One can
program a computer on several levels. Machine code, the actual
binary language of the computer itself, is one method of
specifying instructions. However, it is tedious to write and prone
to error. Assembly language, which uses mnemonics for instructions
(e.g., ADD in place of a 3-bit operation code) and, depending on
its sophistication, handles addressing, is at a higher level. Most
programmers in the early 1960s were quite familiar with assembly
languages, but such programs suffered from the need to put too
much responsibility in the hands of the programmer. For Apollo,
MIT developed a special higher order language that translated
programs into a series of subroutine linkages, which were
interpreted at execution time. This was slower than a comparable
assembly language program, but the language required less storage
to do the same job92. The average instruction required two machine
cycle-about 24 milliseconds-to execute93.
The interpreter got a starting location in
memory, retrieved the data in that location, and interpreted the data
as though it were an instruction94. Instead of
having only the 11 instructions available in assembler, up to 128
pseudoinstructions were defined95. The larger number of instructions in the interpreter
meant that equations did not have to be broken down
excessively96. This increased the speed and accuracy of the
coding.
- The MIT staff gave the resulting computer
programs a variety of imaginative names. Many, such as SUNDISK,
SUNBURST, and SUNDIAL, related to the sun because Apollo was the
god of the sun in the classical period. But the two major lunar
flight programs were called COLOSSUS and LUMINARY. The former was
chosen because it began with "C" like the CM, and the latter
because it began with "L" like the LEM97. Correspondence between NASA and MIT often
shortened these program names and appended numbers. For example,
SOLRUM55 was the 55th revision of SOLARIUM for the AS501 and 502
missions. BURST116 was the 116th revision of
SUNBURST98. Although these programs had many similarities,
COLOSSUS and LUMINARY were the only ones capable of navigating a
flight to the moon. On August 9, 1968, planners decided to put the
first released version of COLOSSUS on Apollo 8, which made the
first circumlunar flight possible on that
mission99.
-
-
- Handling Restarts
-
-
- One of the most significant differences
between batch-type [46] computer
systems and real-time systems is the fact that in the latter, an
abnormal termination of a program is not acceptable. If a
ground-based, non-real-time computer system suffers a software
failure ("goes down") due to overloads or mismanagement of
resources, it can usually be brought up again without serious
damage to the users. However, a failure in a real-time system such
as that in an aircraft may result in loss of life. Such systems
are backed up in many ways, but considerable emphasis is still
placed on making them failure proof from the start. Obviously, the
AGC had to be able to recover from software failures. A worstcase
example would be a failure of the computer during an engine burn.
The system had to have a method of staying "up" at all
times.
-
- The solution was to provide for restarts
in case of software failures. Such restarts could be caused by a
number of conditions: voltage failures, clock failure, a "rupt
lock" in which the system got stuck in interrupt mode, or a signal
from the NIGHT WATCHMAN program, which checked to see if the
NEWJOB register had not been tested by the EXECUTIVE, indicating
that the operating system was hung up in some
way100.
-
- An Apollo restart transferred control to a
specified address, where a program would begin that consulted
phase tables to see which jobs to schedule first. These jobs would
then be directed to pick up from the last restart point. The
restart point addresses were kept in a restart table. Programmers
had to ensure that the restart table entries and phase table
entries were kept up to date by the software as it
executed101. The restart program also cleared all output
channels, such as control jet commands, warning lights, and engine
on and off commands, so that nothing dangerous would take place
outside of computer control102 .
-
- A software failure causing restarts
occurred during the Apollo 11 lunar landing. The software was
designed to give counter increment requests priority over
instructions103. This meant that if some item of hardware needed to
increment the count in a memory register, its request to do so
would cause the operating system to interrupt current jobs,
process the request, and then pick up the suspended routines. It
had been projected that if 85,000 increments arrived in a second,
the effect would be to completely stop all other work in the
system104. Even a smaller
number of requests would slow the software down to the point at
which a restart might occur. During the descent of Apollo 11 to
the moon, the rendezvous radar made so many increment requests
that about 15% of the computer systems resources were tied up in
responding105. The time spent handling the interrupts meant that
the interrupted jobs did not have enough computer time to complete
before they were scheduled to begin again. This situation caused
restarts to occur, three of which happened in a 40-second period
while program P64 of LUMINARY ran during
descent106. The restarts [47] caused a
series of warnings to be displayed both in the spacecraft and in
Mission Control. Steven G. Bales and John R. Garman, monitoring
the computer from Mission Control, recognized the origin of the
problem. After consultation, Bales, reporting to the Flight
Director, called the system GO for landing107. They were right, and the restart software
successfully handled the situation. The solution to this
particular problem was to correct a switch position on the
rendezvous radar which, through an arcane series of circuitry, had
caused the analog-to-digital conversion circuitry to race up and
down108. This incident proved the need for and
effectiveness of built-in software recovery for unknown or
unanticipated error conditions in flight software-a philosophy
that has appeared deeply embedded in all NASA manned spaceflight
software since then.
-
-
- Verification and
Validation
-
-
- There could be no true certification of
the Apollo software because it was impossible to simulate the
actual conditions under which the software was to operate, such as
zero-G. The need for reliability motivated an extensive testing
program consisting of simulations that could be accomplished
before flight. Three simulation systems were available for
verification purposes: all-digital, hybrid, and system test labs.
All-digital simulations were performed on the Honeywell 1800s and
IBM 360s used for software development. Their execution rate was
10% of real time109. Technicians did hybrid simulations in a lab that
contained an actual AGC with a core rope simulator (as core rope
would not be manufactured until after verification of the program)
and an actual DSKY. Additionally, an attached Beckman analog
computer and various interfaces simulated spacecraft responses to
computer commands110. Further ad hoc verification took place in the
mission trainers located in Houston and at Cape Canaveral, which
would run the released programs in their interpretive
simulators.
-
- The simulations followed individual unit
tests and integrated tests of portions of the software. At first,
MIT left these tests to the programmers to be done on an informal
basis. It was very difficult at first to get the Instrumentation
Laboratory to supply test plans to NASA111. The need for formal validation rose with the size
of the software. Programs of 2,000 instructions took between 50
and 100 test runs to be fully debugged, and full-size mission
loads took from 1,000 to 1,200 runs112.
-
- NASA exerted some pressure on MIT to be
more consistent in testing, and it eventually adopted a four-level
test structure based largely on the verification of the Gemini
Mission Control Center developed by IBM in
1964113. This is important because formal [48] release of
the program for rope manufacture was dependent on the digital
simulations only. Raytheon performed the hybrid and system tests
after they had the release tape in hand114. At that time, MIT would have released an AGC
Program Verification Document to NASA. Aside from help from IBM,
NASA also had TRW participate in developing test plans. Having an
outside group do some work on verification is a sound software
engineering principle, as it is less likely to have a vested
interest in seeing the software quickly succeed, and it helps
prevent generic errors.
-
-
- Apollo Software Development
Problems
-
-
- Real-time flight software development on
this scale was a new experience for both NASA and the MIT
Instrumentation Laboratory. Memory limitations affected the
software so that some features and functions had to be abandoned,
whereas tricky programming techniques saved others. Quality of the
initial code was sometimes poor, so verification took longer and
was more expensive. Despite valiant validation efforts, software
bugs remained in released programs, forcing adjustments by users.
Several times, NASA administrators put pressure on MIT, to reduce
software complexity because there were real doubts about MIT's
ability to deliver reliable software on time. Apparently, few had
anticipated that software would become a pacing item for Apollo,
nor did they properly anticipate solutions to the problems.
-
- By early 1966, program requirements even
exceeded the Block H computer's memory. A May software status memo
stated that not only would the programs for the AS504 mission
(earth orbit with a LEM) exceed the memory capacity by 11,800
words but that the delivery date for the simpler AS207/208
programs would be too late for the scheduled
launch115. Lack of memory and the need for faster throughput
resulted in complicating and delaying the program development
effort116. One of MIT's top managers explained
- If you are limited in program capacity ...
you have to fix. You have to get ingenious, and as soon as you
start to get ingenious you get intermeshing programs, programs
that depend upon others and utilize other parts of those, and many
things are going on simultaneously. So it gets difficult to assign
out little task groups to program part of the computer; you have
to do it with a very technical team that understands all the
interactions on all these things117.
-
-
- The development of obscure code caused
problems both in understanding the programs and validating them,
and this, in turn, caused delays. MIT's considerable geographic
distance from Houston caused [49] additional
problems. Thus, NASA's contract managers had to commute often.
Howard W. "Bill" Tindall, newly assigned from the Gemini Project
as NASA's "watchdog" for MIT software, spent 2 or 3 days a week in
Boston starting in early 1966118.
-
- Tindall was well known at the Manned
Spacecraft Center due to his legendary "Tindallgrams" - blunt
memos regarding software development for Apollo. One of the first
to recognize the importance of software to mission schedules, he
wrote on May 31, 1966 that "the computer programs for the Apollo
spacecraft will soon become the most pacing item for the Apollo
flights119. MIT was about to make the standard emergency move
when software was in danger of being late: to throw more bodies
into the project, a tactic that often backfires. As many as 50
people were to be added to the programming staff, and the amount
of interaction between programmers and, thus, the potential for
miscommunication increased along with the time necessary to train
newcomers. MIT tried to protect the tenure of its permanent staff
by using contractors who could be easily released. The hardware
effort peaked at 600 workers in June of 1965 and fell off rapidly
after that, while software workers steadily increased to 400 by
August of 1968. With the completion of the basic version of
COLOSSUS and LUMINARY, the number of programmers quickly
decreased120. This method, although in the long-term interests
of the laboratory, caused considerable waste of resources in
communication and training.
-
- Tindall's memo also detailed many of
NASA's efforts to improve MIT's handling of the software
development. Tindall had taken Lynwood Dunseith, then head of the
computer systems in Mission Control, and Richard Hanrahan of IBM
to MIT to brief the Instrumentation Laboratory on the Program
Development Plan used for management of software development in
the Real-Time Computing Center associated with Mission Control.
The objective was to give MIT some suggestions on measuring
progress and detecting problem areas early. One NASA manager
pointed out that the Instrumentation Laboratory was protective of
the image of MIT, and one way to control MIT was to threaten its
self-esteem121. The need to call on IBM for advice was apparently
a form of negative motivation. A couple of weeks later, Tindall
reported that Edward Copps of MIT was leading the development of a
Program Development Plan based on one done by
IBM122. However, by July he was complaining that MIT was
implementing it too slowly123. In fact, some aspects of configuration control
such as discrepancy reporting (when the software does not match
the specification) took over a year for MIT to
implement124.
-
- NASA had to be very careful in approving
cuts in the program requirements to achieve some memory savings.
Some features were obviously "frosting," and could easily be
eliminated; for example, the effects of the oblate nature of the
earth, formerly figured into lunar orbit [50] rendezvous
but actually minimal enough to be ignored125. Also cut were some attitude maneuver computations.
They therefore left Reaction Control System (RCS) burns to the
"feel" of the pilot, which meant slightly greater fuel
expenditure126. Overall, the cuts resulted in software that saved
money and accelerated development but could not minimize fuel
expenditures nor provide the close guidance tolerance that was
within the capability of the computer, given more
memory127.
-
-
- Flight AS-204: A Breaking
Point
-
-
- Despite efforts by both MIT and NASA, by
the summer of 1966, flight schedules and problems in development
put both organizations in a dangerous position regarding the
software. A study of the problems encountered with the software
for flight AS-204 which was to be the first manned Apollo mission,
best demonstrates the urgency. On June 13, Tindall reported that
the AS-204 program undergoing integrated tests had bugs in every
module. Some had not been unit tested prior to being
integrated128. This was a serious breach of software engineering
practice. If individual modules are unit tested and proven
bug-free, then bugs found in integrated tests are most likely
located in the interfaces or calling modules. If unit testing has
not been done then bugs could be anywhere in the program load, and
it is very difficult to identify the location properly. This
vastly increases the time and, thus, the cost of debugging. It
causes a much greater slip in schedule than time spent on unit
tests. Even worse, Tindall said that the test results would not be
formally documented to NASA but that they would be on file if
needed.
-
- The AS-204 software schedule problems
affected other things. All the crew-requested changes in the
programs were rejected because including them would cause even
further delays129. The AS-501 program and others began to slip
because the AS-204 fixes were saturating the Honeywell 1800s used
in program development130. MIT also added another nine programmers to the
team, all from AC Electronic, thus increasing communication and
training problems.
-
- The eventual result was that the flight
software for the mission was of dubious quality. Tindall predicted
such would be the case as early as June 1966, saying that we have
every expectation that the flight program we finally must accept
will be of less than desirable quality131. In other words, it would contain bugs, bugs that
would not actually threaten the mission directly but that would
have to be worked around either by the crew or by ground control.
They found one such bug less than a month before the scheduled
February 21, 1967, launch date. Ground computers and the Apollo
guidance [51] computer calculated the time for the de-orbit
burn that preceded re-entry. Simulations performed during January
1967 and reported on the 23rd indicated that there was a
discrepancy between the two calculations of as much as 138
seconds! Since the core rope was already installed in the
spacecraft, the only possible fix (besides a delay in the launch
time) would be to have the crew ignore the Apollo computer
solution. The ground would transmit the Real-Time Computing Center
solution, after which an astronaut would have to key the numbers
into the Apollo computer132. This situation, and other discrepancies, led one
NASA engineer to later remark that we were about to fly with
flight software that was really suspect 133.
-
- AS-204 did not fly, so that software load
was never fully tried. On January 27 1967, during a simulation
with the crew in the spacecraft on the pad, a fire destroyed the
CM, killed the crew, and delayed the Apollo program for months.
The changes in managing software development put into effect by
NASA and MIT during 1966 had not had enough time to take effect
before the fire. In the ensuing period, with manned launches on
indefinite delay, MIT was under the direction of the NASA team led
by Tindall and was able to catch up on its work and take steps to
make the software more reliable. NASA and MIT split the effort
among three programs: CM earth orbit, CM lunar orbit, and lunar
module lunar landing (LM earth orbit was
dropped)134. By October 17, 1967, the SUNDISK earth orbit
program was complete, verified, and ready for core rope
manufacture, a year before the first manned
flight135. The time gained by the delay caused by the fire
allowed for significant improvements in the Apollo software.
Tindall observed at the time, It is becoming evident that we are
entering a new epoch regarding development of spacecraft computer
programs. No longer would programs be declared complete in order
to meet schedules, requiring the users to work around errors.
Instead quality would be the primary
consideration136.
-
-
- The Guidance Software Task
Force
-
-
- Despite postfire improvements, Apollo
software had more hurdles to clear. NASA was aware of continuing
concern about Apollo's computer programs. Associate Administrator
for Manned Spaceflight George E. Mueller formed a Guidance
Software Task Force on December 18, 1967 to study ways of
improving development and verification* . The group met 14 times at various locations
before its final report in September 1968137.
-
- [52] Even while
the Task Force was investigating, Mueller took other steps to
challenge MIT. A Software Review Board re-examined the software
requirements for the lunar mission in early February 1968. The
board judged the programs to be too sophisticated and complex, and
Mueller requested that they aim for a 50% reduction in the
programs, with increased propellant consumption allowed as a
tradeoff138. An aide reported that Mueller was convinced that
MIT "might not provide a reliable, checked-out program on
schedule" for the lunar landing mission139.
-
- The recommended 50% scrub did not occur,
and the final report of the Task Force was very sympathetic to the
problems involved in developing flight software. It recommended
standardization of symbols, constants, and variable names used at
both Houston and Huntsville to make communication and coding
easier140. The Task Force acknowledged that requirements
would always be dynamic and that development schedules would
always be accelerated, but rather than using this for an excuse
for poor quality, the group recommended that software not be
slighted in future manned programs. Adequate resources and
personnel were to be assigned early to this "vital and
underestimated area141". This realization would have great effect on
managing later software development for the Space Transportation
System.
-
- Mueller remained concerned about software
even after the Task Force dissolved. On March 6, 1969, he wrote a
letter to Robert Gilruth, NASA deputy administrator, complaining
that software changes were being made too haphazardly and should
receive more attention, equal to that given to hardware change
requests. Gilruth replied five days later, disagreeing, noting
that the Configuration Control Board and other committees formed
an interlocking system adequate for change
control142.
-
-
- Lessons of the Apollo Software
Development Process
-
-
- Overcoming the problems of the Apollo
software, NASA did successfully land a man on the moon using
programs certifiably adequate for the purpose. No one doubted the
quality of the software eventually produced by MIT nor the
dedication and ability of the programmers and managers at the
Instrumentation Lab. It was the process used in software
development that caused great concern, and NASA helped to improve
it143. The lessons of this endeavor were the same learned
by almost every other large system development team of the 1960s:
(a) documentation is crucial, (b) verification must proceed
through several levels, (c) requirements must be clearly defined
and carefully managed, (d) good development plans should be
created and [53] executed, and (e) more programmers do not
mean faster development. Fortunately, no software disasters
occurred as a result of the rush to the moon, which is more a
tribute to the ability of the individuals doing the work than to
the quality of the tools they used.
* Members of the
Task Force included Richard H. Battin, MIT; Leon R. Bush, Aerospace
Corp.; Donald R.Hagner, Bellcomm; Dick Hanrahan; IBM; James S.
Martin, NASA-Langley; John P. Mayer, NASA-MSC; Clarence Pitman; TRW;
and Ludie G.Richard; NASA-Marshall. Mueller was the chairman.