Report of the PRESIDENTIAL COMMISSION
on the Space Shuttle Challenger Accident
Volume 4 Index
Hearings of the Presidential
Commission on the Space Shuttle Challenger Accident: February 6, 1986
to February 25, 1986
FEBRUARY 10, 1986 SESSION
[318] [Ref. 2/10-18]
General Conclusions.
- All O-ring erosion has occurred where gas
paths in the vacuum putty are formed
- Gas paths in the vacuum putty can occur
during assembly, leak check, or during motor pressurization
- Improved filler materials or layup
configurations which still allow a valid leak check of the primary
O-rings may reduce frequency of O-ring erosion but will probably
not eliminate it or reduce the severity of erosion
- Elimination of vacuum putty in a tighter
joint area will eliminate O-ring erosion if circumferential flow
is not present - if it is present, some baffle arrangement may be
required
- Erosion in the nozzle joint is more severe
due to eccentricity; however, the secondary seal in the nozzle
will seal and will not erode through
- The primary O-ring in the field joint
should not erode through but if it leaks due to erosion or lack of
sealing the secondary seal may not seal the motor
[Ref. 2/10-19] Recommendations.
- The lack of a good secondary seal in the
field joint is most critical and ways to reduce joint rotation
should be incorporated as soon as possible to reduce
criticality
- The flow conditions in the joint areas
during ignition and motor operation need to be established through
cold flow modeling to eliminate O-ring erosion
- QM-5 static test should be used to qualify
a second source of the only flight certified joint filler material
(asbestos-filled vacuum putty) to protect the flight program
schedule
- VLS-1 should use the only flight certified
joint filler material (Randolph asbestos-filled vacuum putty) in
all joints
- Additional hot and cold subscale tests
need to be conducted to improve analytical modeling of O-ring
erosion problem and for establishing margins safety for eroded
O-rings
- Analysis of existing data indicates that
it is safe to continue flying existing design as long as all
joints are leak checked with a 200 psig stabilization pressure,
are free of contamination in the seal areas and meet O-ring
squeeze requirements
- Efforts needs to continue at an
accelerated pace to eliminate SRM seal erosion
Back