NASA Investigation Board Report On The INITIAL FLIGHT ANOMALIES OF SKYLAB 1

CHAPTER IX : THE SKYLAB MANAGEMENT SYSTEM

The management system utilized for the Skylab program was derived directly from that which had been developed and used in the Apollo program. As such, it included a series of formal reviews and certifications at progressive points in the program life cycle that are intended to provide visibility to contractor and NASA management on program status, problems and their resolution.. The selected review points and their primary purpose are set forth in Skylab Program Directive No. 11A, which is summarized as follows:

PRR   

Preliminary Requirements Review. "To verify by formal review the suitability of the conceptual configuration and to establish the requirements and action necessary to achieve a design baseline."

PDR   

Preliminary Design Review. "To verify by formal review the suitability of the baseline design of the Contract End Item."

CDR   

Critical Design Review. "To verify by formal review the suitability of the design of a Contract End Item when the design is essentially complete."

CI   

Configuration Inspection. "To certify that the configuration for the Contract End Item as being offered for delivery is in conformance with the baseline established at the CDR."

COFW   

Certification of Flight Worthiness. "To certify that each flight stage module and experiment is a complete and qualified item of hardware prior to shipment."

DCR   

Design Certification Review. "To examine the design of the total mission complex for proof of design and development maturity."

FRR   

Flight Readiness Review. "A consolidated re view of the hardware, operational and support elements to assess their readiness to begin the mission."

The primary thrust of these key program milestones is thus a formal review and certification of equipment design or program status; the primary purpose being served is to provide visibility into these matters to senior NASA and contractor program management. As noted in the Skylab Program Directive, the organization and conduct of the review is a major responsibility of a senior program or management official. For each review, specific objectives are to be satisfied, in conformance with preestablished criteria and supported by specified documentation. The reviews are, thus highly structured and formal in nature, with a major emphasis on design details, status of various items and thoroughness of documentation. Several hundred specialists, subsystem engineers and schedule managers are generally in attendance.

The material presented in these reviews is, of course, developed over a period of time in many lower-level reviews and in monthly progress reports dealing with various systems and subsystems. In addition, several other major reviews peculiar to Skylab were conducted, including the following:

Cluster System Review of December 1967

Mathews' Subsystem Review Team of August 1970 - July 1971

Critical Mechanisms Review of March 1971

Systems Operations Compatibility Assessment Review of October 1971 - June 1972

Structural/Mechanical Subsystem Reviews of July 1971 - May 1972

Hardware Integrity Review of March 1973

MSM Center Directors' Program Reviews

There was thus no shortage of reviews. In order to determine the consideration given to the meteoroid shield throughout the program, the Board examined the minutes, presentation material, action items, and close-out of data of each of these reviews and progress reports. In every case, complete records and documentation were available for inspection. In no case did the Board uncover any conflict or inconsistency in the record. All reviews appeared to be in complete conformance to Program Directive 11A and were attended by personnel appropriate to the subject matter under consideration. The system was fully operational.

And yet, a major omission occurred throughout this process - consideration of aerodynamic loads on the meteoroid shield during the launch phase of the mission. Throughout this six.year period of progressive reviews and certifications the principal attention devoted to the meteoroid shield was that of achieving a satisfactory deployment in orbit and containment of the ordnance used to initiate the deployment. As noted in the preceding section on possible failure modes, design attention was also given to the strength of the hinges, trunnion straps and bolts, to the crushing pressures on the frames of the auxiliary tunnel, to flutter and to the venting of both the auxiliary tunnel and the several panels of the shield. But never did the matter of aerodynamic loads on the shield or aeroelastic interactions between the shield and its external pressure environment during launch receive the attention and understanding during the design and review process which in retrospect it deserved.

This omission, serious as it was, is not surprising. From the beginning, a basic design concept and requirement was that the shield be tight to the tank. As clearly stated in much of the early documentation, the meteoroid shield was to be structurally integral with the S-IVB tank - a piece of structure that was well proven in many previous flights. The auxiliary tunnel frames, the controlled torque on the trunnion bolts and the rigging procedure itself were all specifically intended to keep the shield tight against the tank. The question of whether the shield would stay there under the dynamics of flight through the atmosphere was simply not considered in any coordinated manner - at least insofar as the Board could determine by this concentrated investigation.

Possibly contributing to this oversight was the basic view of the meteoroid shield as a piece of structure. Organizationally, responsibility for the meteoroid shield at MDAC-W was established to develop it as one of the several structural subsystems, along with such items as spacecraft structure and penetrations, pressure vessels, scientific airlocks, protective covers and finishes. Neither the government, (MSFC), or the contractor, (MDAC-W), had a full-time subsystem engineer assigned to the meteoroid shield. While it is recognized that one cannot have a full-time engineer on every piece of equipment, it is nonetheless possible that the complex interactions and integration of aero-dynamics, structure, rigging procedures, ordnance, deployment mechanisms, and thermal requirements of the meteoroid shield would have been enhanced by such an arrangement. Clearly, a serious failure of communications among aerodynamics, structures, manufacturing and assembly personnel, and a breakdown of a systems engineering approach to the shield, existed over a considerable period of time. Further, the extensive management review and certification process itself, in its primary purpose of providing visibility of program status to management, did not identify these faults.

Further insight into this treatment of the meteoroid shield as one of several structural subsystems is obtained by a comparison of a listing of the design reviews conducted on both the MS and the SAS. At MDAC-W, the SAS was considered a major subsystem and was placed under the direction of a full-time project engineer. A comparison of the design reviews held jointly between MDAC-W and MSFC on the MS and on the SAS is presented in tables IX-1 and IX-2, respectively. The more concentrated and dedicated treatment received by the SAS is evident in this comparison.

The Board is impressed with the thoroughness, rigor and formalism of the management review system developed by Apollo and used by Skylab. Great discipline is imposed upon everyone by this system and it has served very well. In a large program as geographically dispersed and intrinsically complex as Skylab, such visibility of program status and problems, is a management necessity. We therefore have no wish to alter this management system in any basic manner. But all systems created by man have their potential flaws and inherent hazards. Such inherent flaws and weaknesses must be understood by those who operate the system if it is not to become their master. We therefore wish to identify some of those potential flaws as they have occurred to us in this investigation, not to find fault or to identify a specific cause of this particular flight failure but to use this experience to further strengthen the management processes of large and complex endeavors.

As previously noted the management system developed by NASA for manned space flight places large emphasis on rigor, detail and thoroughness. In hand with this emphasis comes formalism, extensive documentation, and visibility in detail to senior management. While nearly perfect, such a system can submerge the concerned individual and depress the role of the intuitive engineer or analyst. It may not allow full play for the intuitive judgment or past experience of the individual. An emphasis on management systems, can, in itself, serve to separate the people engaged in the program from the real world of hardware. To counteract these potential hazards and flaws, we offer the following suggestions.

Table IX-1 ORBITAL WORKSHOP PROGRAM METEOROID SHIELD DESIGN REVIEWS

Date   

 Title

May 1967   

 OWS Preliminary Design Review (PDR)

Feb 1970   

 MS Internal Design Review QDR)

Feb 1970   

 MS Workshop Design Review (WDR)

Sep 1970   

 OWS Critical Design Review (CDR)

Mar 1971   

 OWS Ordnance & Deployment System Review

Jun 1971   

 MS Test Review

Jul 1971   

 Structures, Propulsion & Thermal Control Subsystem Review

Sep 1971   

 Environmental Control, Pneumatic, Structures & Ordnance Subsystem Review

Oct 1971   

 Environmental Control, Pneumatic, Structures & Ordnance Subsystem Review

Nov 1971   

 Pneumatic, Structures, Environmental Control Subsystem Review

Jan 1972   

 Structures, Ordnance & Pneumatic Subsystem Review

Mar 1972   

 Structures, Ordnance & Pneumatic S ubsystem Review

May 1972   

TACS, Structures, Pneumatic Subsystem Review

Jun 1972   

OWS Structural Subsystem DCR

Oct 1972   

 OWS Design Certification Review (DCR)

Mar 1973   

 OWS Flight Readiness Review (HIR)

Apr 1973   

 OWS Flight Readiness. Review (FRR)

Table IX-2 ORBITAL WORKSHOP PROGRAM SOLAR ARRAY SYSTEM DESIGN REVIEWS

Date   

 Title

Feb, 1970   

 SAS Internal Design Review (IDR)

Jun 1970   

 SAS Workshop Design Review (WDR)

Jun 1970   

 SAS Preliminary Design Review (PDR)

Jan 1971   

 SAS Critical Design Review (CDR)

Mar 1971   

 OWS Ordnance & Deployment System Review

Jun 1971   

 SAS Subsystem Review

Sep 1971   

 SAS Subsystem Review

Oct 1971   

 SAS Subsystem Review

Nov 1971   

 SAS Subsystem Review

Dec 1971   

 SAS Subsystem Review

Jan 1972   

 SAS Subsystem Review

Mar 1972   

 SAS Subsystem Review

Apr 1972   

 SAS Subsystem Review

May 1972   

 SAS Subsystem Review

Jun 1972   

 OWS Structural Subsystem DCR

Oct 1972   

 OWS Design Certification Review (DCR)

Mar 1973   

 OWS Hardware Integrity Review (HIR)

Apr 1973   

 OWS Flight Readiness Review (FRR)


link to the previous pagelink to the index pagelink to the next page