Source: NASA Historical Reference Collection, NASA History Office, NASA Headquarters, Washington, DC.
I. Introduction
This is the report of the NASA's Management Review of North American Aviation Corporation management of Saturn II Stage (S-II) and Command and Service Module (CSM) programs. The Review was conducted as a result of the continual failure of NAA to achieve the progress required to support the objective of the Apollo Program.
The scope of the review included an examination of the Corporate organization and its relationship to and influence on the activities of S&ID, the operating Division charged with the execution of the S-II and CSM programs. The review also included examination of NAA off-site program activities at KSC and MTF.
The members of the review team were specifically chosen for their experience with S&ID and their intimate knowledge of the S-II and CSM programs. The Review findings, therefore, are a culmination of the judgements of responsible government personnel directly involved with these programs. The team report represents an assessment of the contractor's performance and existing conditions affecting current and future progress, and recommends actions believed necessary to achieve an early return to the position supporting Apollo program objectives.
The Review was conducted from November 22 through December 6 and was organized into a Basic Team, responsible for over-all [2] assessment of the contractor's activities and the relationships among his organizational elements and functions; and sub-teams who assessed the contractor's activities in the following areas:
Review Team membership is shown in Appendix 7.
Team findings and recommendations were presented to NAA Corporate and S&ID management on December 19.
II. NAA's Performance to Date - Ability to Meet Commitments.
At the start of the CSM and S-II Programs, key milestones were agreed upon, performance requirements established and cost plans developed. These were essentially commitments made by NAA to NASA. As the program progressed NASA has been forced to accept slippages in key milestone accomplishments, degradation in hardware performance, and increasing costs.
I. S-II--1.Schedules
As reflected in Appendix VI key performance milestones in testing, as well as end item hardware deliveries, have slipped continuously in spite of deletions of both hardware and test content. The fact that the delivery [3] of the common bulkhead test article was rescheduled 5 times, for a total slippage of more than a year, the All System firing rescheduled 5 times for a total slippage of more than a year, and S-II-1 and S-II-2 flight stage deliveries rescheduled several times for a total slippage of more than a year, are indicative of NAA's inability to stay within planned schedules. Although the total Apollo program was reoriented during this time, the S-II flight stages have remained behind schedules even after this reorientation.
III. NASA Assessment - Probability of NAA Meeting Future Commitments
A. CSM
Today, after 4 1/2 years and a little more than a year before first flight, there are still significant technical problems and unknowns affecting the stage. Manufacture is at least 5 months behind schedule. NAA's continued inability to meet internal objectives, as evidenced by 5 changes in the manufacturing plan in the last 3 months, clearly indicates that extraordinary effort will be required if the contractor is to hold the current position, let alone better it. The MTF activation program is being seriously affected by the insulation repairs and other work required on All Systems stage. The contractor's most recent schedule reveals further slippage in completion of insulation repair. Further, integration of manual GSE has recently slipped 3 weeks as a result of configuration discrepancies discovered during engineering checkout of the system. Failures in timely [6] and complete engineering support, poor workmanship, and other conditions have also contributed to the current S-II situation. Factors which have caused these problems still exist. The two recent funding requirements exercises, with their widely different results, coupled with NAA's demonstrated history of unreliable forecasting, as shown in Appendix VI, leave little basis for confidence in the contractor's ability to accomplish the required work within the funds estimated. The team did not find significant indications of actions underway to build confidence that future progress will be better than past performance.
B.CSM
With the first unmanned flight spacecraft finally delivered to KSC, there are still significant problems remaining for Block I and Block II CSM's. Technical problems with electrical power capacity, service propulsion, structural integrity, weight growth, etc. have yet to be resolved. Test stand activation and undersupport of GSE still retard schedule progress. Delayed and compromised ground and qualification test programs give us serious concern that fully qualified flight vehicles will not be available to support the lunar landing program. NAA's inability to meet spacecraft contract use deliveries has caused rescheduling of the total Apollo program. Appendix VI indicates the contractor's schedule trends which cause NASA to have little confidence that the S&ID will meet its future spacecraft commitments. While our management review indicated that some progress is [7] being made to improve the CSM outlook, there is little confidence that NAA will meet its schedule and performance commitments within the funds available for this portion of the Apollo program.
IV. Summary Findings Presented below is a summary of the team's views on those program conditions and fundamental management deficiencies that are impeding program progress and that require resolution by NAA to ensure that the CSM and S-II Programs regain the required program position. The detail findings and recommendations of the individual sub-team reviews are Appendix to this report.
A. NAA performance on both programs is characterized by continued failure to meet committed schedule dates with required technical performance and within costs. There is no evidence of current improvement in NAA's management of these programs of the magnitude required to give confidence that NAA performance will improve at the rate required to meet established Apollo program objectives.
B. Corporate interest in, and attention to, S&ID performance against the customer's stated requirements on these programs is considers passive. With the exception of the recent General Office survey of selected functional areas of S&ID, the main area of Corporate level interest appears to be in S&ID's financial outlook and in their cost estimating and proposal efforts. While we consider it appropriate that the responsibility and authority for execution of NASA programs be vested in the operating Division, this does not relieve the Corporation of its responsibility, and accountability to NASA for results. [9] We do not suggest that another level of program management be established in the Corporate staff, but we do recommend that the Corporate Office sincerely concern itself with how well S&ID is performing to customer requirements and ensure that responsible and effective actions are taken to meet commitments.
C. Organization and Manning
We consider the program organization structure and assignment of competent people within the organization a prerogative of the manager and his team that have been given the program job to do. However, in view of what we consider to be an extremely critical situation at S&ID, one expected result of the NASA review might be the direction of certain reorganizations and reassignments considered appropriate, by NASA, to improve the situation. While we do have some suggestions for NAA consideration on this subject, they are to be accepted as such and not considered directive in nature. We emphasize that we clearly expect NAA/S&ID to take responsible and thoroughly considered actions on the organization and assignment of people required to accomplish the S-II and CSM Programs. We expect full consideration, in this judgement by NAA, of both near and long term benefits of changes that are made.
Frankly stated--we firmly believe that S&ID is overmaned and that the S-II and CSM Programs can be done, and done better, with fewer people. This is not to suggest that an arbitrary [10] percentage reduction should be applied to each element of S&ID, but we do suggest the need for adjustments, based on a reassessment and clear definition of organizational responsibilities and task assignments.
It is our view that the total Engineering, Manufacturing, Quality, and Program Control functions are too diversely spread and in too many layers throughout the S&ID organization to contribute, in an integrated and effective manner, to the hard core requirements of the programs. The present proliferation of the functions invites non-contributing, "make-work" use of manpower and dollars as well as impediments to program progress.
We question the true strength and authority of each Program Manager and his real ability to be fully accountable for results when he directly controls less that 50% of the manpower effort that goes into his program. This suggests the need for an objective reappraisal of the people and functions assigned to Central versus Program organizations. This should be done with full recognition that the Central organization's primary reason for existence is to support the requirements of the Program Managers. Concurrently, the Program Manager should undertake a thorough and objective "audit" of all current and planned tasks, as well as evaluate the people assigned to these tasks, in order to bring the total effort down to that effort down to that which truly contributes to the program.
It is our opinion that the assignment of the Florida Facility to the Test and Quality Assurance organization creates an anomaly since the Florida activities clearly relate to direct program responsibilities. We recognize that the existence of both CSM and S-II activities at KSC may require the establishment of a single unit for administrative purposes. However, it is our view that the management of this unit is an executive function, rather than one connected with a functional responsibility. We suggest NAA consider a "mirror image" organizational relationship between S&ID and the Florida operation, with the top man at Florida reporting to the S&ID President and the two program organizations reporting to the S&ID Program Managers.
D. Program Planning and Control
Effective planning and control from a program standpoint does not exist. Each organization defines its own job, its own schedules, and its own budget, all of which may not be compatible or developed in a manner required to achieve program objectives. The Program Managers do not define, monitor, or control the interfaces between the various organizations supporting their program.
Organization -- S&ID's planning and control functions are fragmented; responsibility and authority are not clearly defined.
E. Logistics
The CSM and S-II Site Activations and Logistic organizations are adequately staffed to carry out the Logistics support. The problems in the Logistics area are in arriving at a mutual agreement, between NAA and NASA, clearly defining the tasks required to support the programs. The areas requiring actions are as follows:
F. Engineering
The most pronounced deficiencies observed in S&ID Engineering are:
G. Cost Estimating
The "grass roots" estimating technique used at S&ID is a logical step in the process of arriving at program cost estimates and developing operating budgets. However, there are several aspects of the total process that are of concern to NASA:
Several recommendations are made in the appended reports for correcting deficiencies in the estimating process. The basic issue, however, is that an S&ID Management position must be clearly stated and disciplines established to ensure that the end product of the estimating process be only those resources required to do necessary program tasks. In addition, the Program Management must be in an authoritative position that allows him to accept, reject, and negotiate these resource requirements.
H. Manufacturing Work Force Efficiency
There are several indications of less that effective utilization of the manufacturing labor force. Poor workmanship is evidenced by the continual high rates of rejection and MRB actions which result in rework that would not be necessary if the workmanship [16] had been good. This raises a question as to the effectiveness of the PRIDE program which was designed to motivate personnel toward excellence of performance as a result of personal responsibility for the end product. As brought out elsewhere in this report, the ability of Manufacturing to plan and execute its tasks has been severely limited due to continual changing engineering information and lack of visibility as to the expected availability of the engineering information. Recognizing that overtime shifts are necessary at this time, it is our view that strong and knowledgeable supervision of these overtime shifts is necessary, and the a practical system of measuring work accomplished versus work planned must be implemented and used to gauge and to improve the effectiveness of the labor force. The condition of hardware shipped from the factory, with thousands of hours of work to complete, is unsatisfactory to NASA. S&ID must complete all hardware at the factory and further implement, without delay, an accurate system to certify configuration of delivered hardware, properly related to the DD 250.
I. Quality
NAA quality is not up to NASA required standards. This is evidence by the large number of "correction" E.O.'s and manufacturing discrepancies. This deficiency is further compounded [17] by the large number of discrepancies that escape NAA inspectors but are detected by NASA inspectors. NAA must take immediate and effective action to improve the quality of workmanship and to tighten their own inspection. Performance goals for demonstrating high quality must be established, and trend data must be maintained and given serious attention by Management to correct this unsatisfactory condition.
J. Following are additional observations and findings that have resulted from discussions during the Review. Most of them are covered in most detail in the appended sub-team reports. They are considered significant to the objective of improving NAA management of our programs and are therefore highlighted in this section of the report:
The NASA Team views on existing deficiencies in the contractor's management of the S-II and CSM Programs are highlighted in this section of the report and are treated in more detail in the appended sub-team reports. The findings are expressed frankly and result from the team's work in attempting to relate the end results we see in program conditions to fundamental causes for these conditions.
In most instances, recommendations for improvement accompany the findings. In some cases, problems are expressed for which the team has no specific recommendations, other than the need for attention and resolution by NAA.
It is not NASA's intent to dictate solutions to the deficiencies noted in this report. The solution to NAA's internal problems is both a prerogative and a responsibility of NAA Management, within the parameters of NASA's requirements as stated in the contracts. NASA does, however, fully expect objective, responsible, and timely action by NAA to correct the conditions described in this report.
It is recommended that the CSM incentive contract conversion proceed as now planned.
Incentivization of the S-II Program should be delayed until NASA is assured that the S-II Program is under control and a responsible proposal is received from the contractor.
Decision on a follow-on incentive contract for the CSM, beyond the present contract period, will be based on contractor performance.
It is recommended that NAA respond to NASA, by the end of January 1966, on the actions taken and planned to be taken to correct the conditions described in this report. At that time, NAA is also to certify the tasks, schedules, and resource requirements for the S-II and CSM Programs.
It is further recommended that the same NASA Review Team re-visit NAA during March 1966 to review NAA performance in the critical areas described in this report.
Document III-18
December 19, 1965
Mr. J. L. Atwood, President
North American Aviation, Inc.
1700 E. Imperial Highway
El Segundo, California
Dear Lee:
In my letter of October 27, 1965, I conveyed to you the seriousness with which I viewed the state of affairs in both the Apollo and S-II Programs at your Space and Information Systems Division. Phillips' report has not only corroborated my concern, but has convinced me beyond doubt that the situation at S&ID requires positive and substantive actions immediately in order to meet the national objectives of the Apollo Program.
Since I am not sure that you see the performance of S&ID in the same light that I do, let me give you a perspective from my point of view.
When I joined NASA in the Fall of 1963, I restructured the Apollo Program to bring its several elements into balance and to establish a schedule that could be achieved based on the state of development at that time. Since that time, in the spacecraft project, we have found it necessary to:
Omit several sub-systems from 009.
b. Delay flight of 201 from November 65 until probably February or March 66 due to late delivery of 009 and its GSE together with the many difficulties of getting things [2] to work together at the Cape.
c. Reschedule the first manned flight from 203 to 204 to relieve the spacecraft schedule. NAA ability to support the 204 flight scheduled in October 66 now looks doubtful.
d. Reschedule 202 from April to June 1966 because 011 is several months behind schedule. NAA ability to support the June schedule now looks doubtful.
e. Reschedule the first Block II spacecraft flight from 206 in April 67 to 207 in July 67. Late last year, when the Block II Program was defined, your people agreed that they could and would do a better job on Block II engineering and that they would meet their design review and drawing release schedules. I'm very disturbed to learn now that Block II engineering has been neglected and that it is some months behind schedule. To me, considering performance to date, it looks like the danger flags protend delay of the critical 207 flight.
f. Delay the delivery of 008 by several months. This is a critical vehicle to perform thermal vacuum tests in the Houston Chamber as a prerequisite to manned flight. People will argue that the Chamber isn't ready, but we urgently need that spacecraft to get it working as a system vehicle and with its ground equipment and crews.
g. Delete seven boilerplate and flight spacecraft from the Block I Program to reduce cost growth and relieve the schedule to minimize slippage.
I could go on; there are other things that we've had to accommodate such as cost growth, but I believe this list gives you some insight into my evaluation of performance in the spacecraft project. Now, regarding the S-II Project:
a. I am facing the probability that the flight of 501 will be delayed between three and nine months. I [3] assure you that this is due entirely to the status of the S-II stage. It is clear to me that it didn't have to come out this way, and I regret now that I wasn't more insistent a year and a quarter ago when you and I discussed the danger flags then flying, and the possibility of such far reaching actions as transferring the project to your Los Angeles Division.
b. The cost proposal which S&ID presented to MSFC in October of this year was shocking in light of cost projections reported only one month earlier. Perhaps I should even go so far as to suggest that it was irresponsible; in any case, it surely was a gross demonstration of management shortcomings.
c. The Battleship Program is another significant case. You got behind it personally and an ignition test in November 64 resulted; but that achievement was one year behind the original schedule and the test fixture was so devoid of systems as to be little more than a facade. Further, the firing record indicates that only about one-third of the firings really achieved their objectives. The firing program was stopped last April to incorporate flight systems; it has not yet resumed firing.
d. S-II-T is a reel problem. It was delivered late with what was stated to be approximately 21,000 manhours of work to incorporate EO's and perform work that was not completed in the factory due to parts shortages. Today, the work stands at over 50,000 manhours and the firing scheduled for January 66 will most likely occur in March or April. Based on what I have seen so far, I am very concerned that the engineering on which S-II-I is based will require many changes when S-II-T is fired, and further delays of 501 will result.
It is hard for me to understand how a company with the background and demonstrated competence of NAA could have spent 4 1/2 years and more than half a billion dollars on the S-II Project and not yet have fired a stage with flight systems in operation.
Again, I could go on and enumerate additional problems, but the points I have discussed should show you how I see the performance of NAA on these two programs.
I have been in this business long enough to understand quite well the difficulties and setbacks that occur and manifest themselves in many forms in government - industry programs which have as their objective the development, building, and operation of sophisticated systems involving advanced technology and real forward projection of thought. My experience indicates that results are a function of management and technical competence. I submit that the record of these two programs makes it clear that a good job has not been done. Based on what I see going on currently, I have absolutely no confidence that future commitments will be met.
I can see no way of improving future performance, and meeting commitments which NAA must meet if we are to achieve the national objectives of Apollo, except to improve the management and technical competence of your Space and Information systems Division.
Sam Phillips is convinced that S&ID can do a better job with less people. He and his team discussed the reasons why they believe this in their briefing.
I suggest that you can go even further to concentrate management and technical talent on the two programs that constitute 98 percent of the business of S&ID. For example:
a. Eliminate or transfer to another Division those activities at S&ID that are not contributing directly to the progress of the Spacecraft and S-II projects. Examples are the Federal programs Group, parts of the Information Systems Division, and parts of the Advanced Systems Division. This should make possible a substantial consolidation of central engineering and insure that [5] available talent concentrates on the two important programs.
b. Take a hard look at the competence and effectiveness of individuals, especially in the upper echelons of the organization; and move out those who are not really contributing, due either to the organization or to their own competence.
I urge you to consider the potential payoff of extending the project management principle beyond the "designated subsystems project manager" as now practiced in Dale Meyers' organization. I am convinced that there is no substitute for clear assignment of responsibility and accountability to individuals for delivering results. Work packages can be defined quite clearly in both projects and I am sure it is possible to assign responsibility to individuals who are given control of the applicable budget and who are held accountable for delivering on schedule and within budget.
I had hoped that a letter such as this would not be necessary. However, I consider the present situation to be intolerable and can only conclude that drastic action is in the best national interest. I assure you that I have only one purpose, and that is to carry out the Apollo Program on schedule and within planned costs.
I have instructed Sam Phillips to keep his team together so that they can visit S&ID again in March to see if progress is consistent with that required to achieve program objectives.
Sincerely,
/signed/
George E. Mueller
Associate Administrator
For Manned Space Flight
For further information email
histinfo@hq.nasa.gov
Updated October 22, 2004