Report of the PRESIDENTIAL COMMISSION on the Space Shuttle Challenger Accident

Volume 4 Index

Hearings of the Presidential Commission on the Space Shuttle Challenger Accident: February 6, 1986 to February 25, 1986

FEBRUARY 10, 1986 SESSION

 

[272] [Ref.2/10- 1 of 2, 2 of 2]

 

STS-SOLID ROCKET MOTOR O-RING CHRONOLOGY.

4- SEPTEMBER 1980

SPACE SHUTTLE PROGRAM RESPONSE TO VERIFICATION/CERTIFICATION ASSESSMENT - SPECIAL STAFF RECOMMENDATION - PROPULSION

9- DECEMBER 17, 1982

SRB CRITICAL ITEMS LIST

12- MARCH 30, 1984

STS 41-C FLIGHT READINESS REVIEW

16- MARCH 30, 1984

STS 41-C PROGRAMMATIC ACTION ITEM

17- MARCH 1984

PROPULSION DIVISION MONTHLY REVIEW

18- MAY 1984

PROPULSION DIVISION MONTHLY REVIEW

19- NOVEMBER 1984

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

20- DECEMBER 1984

PROPULSION DIVISION MONTHLY REVIEW

21- DECEMBER 1984

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

22- JANUARY 1985

PROPULSION DIVISION MONTHLY REVIEW

23- JANUARY 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

24- FEBRUARY 1985

PROPULSION DIVISION MONTHLY REVIEW

25- FEBRUARY 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

26- FEBRUARY 21, 1985

STS 51-E FLIGHT READINESS REVIEW

28- JUNE 1985

PROPULSION DIVISION MONTHLY REVIEW

29- JUNE 18, 1985

GENERAL MANAGEMENT STATUS REVIEW

31- JUNE 28, 1985

NOTE TO MR. WEEKS FROM MR. WINTERHALTER

36- JULY 2, 1985

STS 51-F FLIGHT READINESS REVIEW


STS - SOLID ROCKET MOTOR D-RING CHRONOLOGY (CONT'D.)

38- JULY 1985

PROPULSION DIVISION MONTHLY REVIEW

42- JULY 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

46- JULY 17, 1985

IRVING DAVIDS MEMORANDUM TO ASSOCIATE ADMINISTRATOR

48- JULY 22, 1985

RUSS BARDOS MEMORANDUM TO MR. WINTERHALTER

50- AUGUST 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

53- AUGUST 15, 1985

STS 51-I FLIGHT READINESS REVIEW

55- AUGUST 19, 1985

MSFC/MTI PRESENTATION TO NASA HEADQUARTERS

56- AUGUST 21, 1985

SRB FY 1987 BUDGET RECOMMENDATION TO ADMINISTRATOR

58- AUGUST 26, 1985

MTI PRELIMINARY SRM NOZZLE/FIELD JOINT SEAL CONCEPTS

134- AUGUST 26, 1985

PAUL HERR MEMORANDUM TO MANAGER, SRB PROJECT (MSFC)

135- AU6UST 30, 1985

MTI PROGRAM PLAN FOR IMPROVEMENT OF SPACE SHUTTLE SRM MOTOR SEALS

151- SEPTEMBER 1985

PROPULSION DIVISION MONTHLY REVIEW

152- SEPTEMBER 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW

154- OCTOBER 2, 1985

MTI ENGINEERING STUDY OF D-RING COMPRESSION SET

172- NOVEMBER 1985

PROPULSION DIVISION MONTHLY REVIEW

174- NOVEMBER 18, 1985

STS 61-B FLIGHT READINESS REVIEW

176- DECEMBER 11, 1985

SRM O-RING TASK FORCE STATUS AND QM 5 RECOMMENDATIONS

198- DECEMBER 1985

PROPULSION DIVISION MONTHLY REVIEW

202- DECEMBER 1985

ASSOCIATE ADMINISTRATOR MONTHLY REVIEW


Back