[1680] [Ref.5/2-28 3 of 14] MSFC Change Sheet for Critical Items List- Solid Rocket Booster and Range Safety Command Destruct System. Change No 23. (continued).

 

MSFC Change Sheet for Critical Items List- Solid Rocket Booster and Range Safety Command Destruct System. Change No 23. (continued).


[1681] [Ref.5/2-28 4 of 14] MSFC Change Sheet for Critical Items List- Solid Rocket Booster and Range Safety Command Destruct System. Change No 23. (continued).

 

 

PAGE A-35

ITEM CODE: 10-01-01

FAILURE MODE: "Leakage at case assembly joints" was reclassified from Category 1R to single failure point. Category 1. See CIL pages A-6A and A-6B for SFP analysis.

 

 


[1682] [ [Ref.5/2-28 5 of 14] MSFC Change Sheet for Critical Items List- Solid Rocket Booster and Range Safety Command Destruct System. Change No 23. (continued).

 

PAGE A-36